Bertha980
An expert review panel concludes that the Highway 99 tunnel project can still be finished on-time, despite significant delays, so far. (WSDOT photo)

Expert report criticizes Seattle tunnel but still confident of budget

An expert review panel concludes that the Highway 99 tunnel project can still be finished on time, despite significant delays, so far.

The panel appointed by Governor Jay Inslee has been studying documents and interviewing project leaders for more than three months.

The 43-page report issued Thursday concludes that the "current budget is likely sufficient" to complete the project, in the first half of 2016. The contractor, Seattle Tunnel Partners, promised completion of the tunnel project by the end of 2015.

Gov. Inslee said the report suggests confidence moving forward with the tunneling project, despite problems so far. "We need to be a vigorous, insistent customer of the contractor," said the Governor. "There are provisions in the agreement with the contract that are fully protective of taxpayers," he assured.

The expert panel believes savings on other parts of the Alaskan Way Viaduct replacement project can keep overall project costs within the $3.1 billion budget.

The report also notes what it calls "communication problems and a strained relationship between the state and the contractor for the Seattle tunneling project.

Todd Trepanier, project manager with the Washington Department of Transporation, says he hasn't read the report yet but spoke generally about the state's relationship with Seattle Tunnel Partners.

"When you have a contract of this magnitude, there's going to be appropriate tension that takes place between the owner and the contractor," he said adding there are open lines of communication between the state and the tunnel contractor.

The expert review panel "observed some confusion from persons internal to the WSDOT organization and with its tunnel partner, STP, with respect to who has the authority and accountability for various aspects and components of the project," according to the report.

"If there wasn't a report in play and you asked me a question: is there confusion on this project, I would answer there is not confusion on this project," said Trepanier. "This project and the responsibilities and what resides with STP and what resides with DOT is well understood."

The tunneling machine known as Bertha has been stalled since early December. A plan is due Friday for how to repair suspected damage to bearing seals. It's expected to take months before tunneling can resume.


Tim Haeck, KIRO Radio Reporter
Tim Haeck is a news reporter with KIRO Radio. While Tim is one of our go-to, no-nonsense reporters, he also has a sensationally dry sense of humor and it will surprise some to learn he is a weekend warrior.
Top Stories

  • 'Boondoggle'
    Seattle's beleaguered tunnel project earns a spot atop a list of 11 'highway boondoggles'

  • 'No War on Cars'
    New head of Seattle DOT on controversies, congestion & the battle between bikes and cars

  • Prost!
    10 people you can't escape at Oktoberfest
ATTENTION COMMENTERS: We've changed our comments, but want to keep you in the conversation.
Please login below with your Facebook, Twitter, Google+ or Disqus account. Existing MyNorthwest account holders will need to create a new Disqus account or use one of the social logins provided below. Thank you.
comments powered by Disqus
Sign up for breaking news e-mail alerts from MyNorthwest.com
In the community
Do you know an exceptional citizen who has impacted and inspired others?
KIRO Radio and WSECU would like to recognize six oustanding citizens this year. Nominate them to be recognized and to receive a $2,000 charitable grant.