CHOKEPOINTS

I-90 work marks milestone for light rail to Bellevue

Apr 2, 2019, 6:03 AM | Updated: 10:51 am

light rail...

(AP)

(AP)

One of the missing links in the construction of the light rail project to Bellevue is the section where the tracks will go over the westbound lanes of I-90 to Bellevue Way.

RELATED: Night closures of I-90 in Bellevue for light rail work

Half of the bridge connecting the tracks from the middle of I-90 to Bellevue Way is now complete, and Monday night, westbound I-90 was closed to remove the “form traveler” that built the bridge. Sound Transit’s Rachelle Cunningham said the “form traveler” builds the structure as it moves, which eliminated the need for a series of freeway closures.

“It moves twelve feet at a time,” she said. “The traveler will move out, pour the concrete, it cures, and then it moves out again. It basically spits it (the concrete) out in front of it.”

That “form traveler” will now be moved to the side of the elevated structure near Bellevue Way, and start building to middle to complete the bridge. You can expect to see some lane and ramp closures in the same area a few more nights this week. The “form traveler” should finish the second half of the bridge in November, which will also require some overnight closures of I-90.

Cunningham said this method of construction just made sense because of the limited space in the area and the freeway below.

“There’s not really any room on the freeway to put the supports that we have over I-405 where they have the form work, and they’re building it that way,” she said. “This method of construction allows us to do it without disrupting the traffic.”

Light rail to Bellevue is now more than 50-percent complete, and it is still on schedule to open in 2023, with the extension to Redmond coming a year later.

Youwill see track being laid on the floating bridge as early as this month.

Chokepoints

I-405 expansion...

Chris Sullivan

Sullivan: I-405 expansion to widen freeway in Bothell is underway

We've all seen I-405 expanding between Bellevue and Redmond, but construction to widen the freeway north of Bothell is now underway as well.

3 days ago

revive i-5 seattle...

Nate Connors

I-5 repair work to slow spring breakers, baseball fans this weekend

Beginning Friday night, three lanes of I-5 north between Albro Place and the West Seattle Bridge through Monday morning at 5 a.m.

6 days ago

Photo: April is Distracted Driving Awareness Month. Washington drivers can face higher insurance ra...

Nate Connors

Has your insurance gone up? Rates can take a hike for distracted drivers

April is Distracted Drivers Awareness Month. The President of NW Insurance Council says it has been working on prevention for years.

8 days ago

Signs in the eight light rail stations will provide real-time travel data for trains and destinatio...

Chris Sullivan

It’s not the whole enchilada, but light rail to roll on Eastside this month

Light rail service on the Eastside begins later this month. The eight stations are ready to roll. Test trains are running on the tracks.

8 days ago

Image: All general-purpose lanes were blocked leaving just the left HOV lane open on I-5 south of 2...

Steve Coogan

Military vehicle accident on I-5 north in Federal Way cleared after snarling traffic

A rollover vehicle accident Wednesday caused significant backups and delays for multiple hours before being cleared.

8 days ago

Rapid-Ride G Line...

Micki Gamez

RapidRide G Line: A new bus route connecting riders to mass transit

King County Metro's (KCM) Al Sanders said the RapidRide G Line will kick off shortly after the Lynwood extension is done in early September.

9 days ago

I-90 work marks milestone for light rail to Bellevue