CHOKEPOINTS

Montlake neighborhood to be isolated for 520 construction this weekend

Aug 26, 2021, 7:04 AM

The Washington Department of Transportation is finishing the initial portion of the lid over SR 520. (KIRO Radio/Chris Sullivan) WSDOT is finishing the initial portion of the lid over SR 520. (KIRO Radio/Chris Sullivan) WSDOT is working on the initial portion of the lid over SR 520. (KIRO Radio/Chris Sullivan) The Montlake Bridge and all access to the neighborhood from the 520 Bridge will be closed this weekend. (KIRO Radio/Chris Sullivan)

Seattle’s Montlake neighborhood is basically off-limits this weekend. Not only is the Montlake Bridge closed, but all access to the neighborhood from the 520 Bridge will be closed too.

What you need to know about month-long Montlake Bridge closure

Montlake will feel like an island for 55 hours this weekend. The Washington Department of Transportation is shutting the area down to finish the initial portion of the lid over State Route 520.

“We are shutting down five of six on or off ramps from the Montlake area, which is unprecedented,” WSDOT’s Steve Peer said. “If you’re traveling to or from here, it’s going to be very, very difficult to get in or out of this neighborhood.”

The only ramp that will be open is the westbound 520 on-ramp from Montlake for residents only, and even they will need a pilot car to maneuver through the construction zone. The closures begin at 10 p.m. Friday night and will last through early Monday morning.

Workers will be moving the northbound and southbound lanes on Montlake Boulevard to the new lid. Those new lanes will be open Monday morning, though the Montlake Bridge closure will last until Sept. 3.

“To be able to do that, we have to have all of these off ramps, Mountlake Boulevard closed, Lake Washington Boulevard closed,” Peer said. “It is a very significant closure. You might say this is a massive closure this weekend.”

Drivers will notice a severe transition to and from the lid from Montlake Boulevard. This is only a temporary configuration until the the lid is completed in about two years. Then a more normal and straight route will be in place.

Peer said they combined this work with the Montlake Bridge closure to keep the delays to a minimum.

“The silver lining to this closure is we’re already closed on the Montlake Bridge,” Peer said. “We’re able to work together so that we don’t have a multitude of closures.”

How is work going on the Montlake Bridge? You might remember that the state is replacing all 84 steel panels that make up the bridge deck. WSDOT engineering manager Ed Kane said they are on schedule to open the bridge on Sept. 3.

“No major surprises,” Kane said about the work so far. “There’s a little bit of miscellaneous steel repair here and there, but we allowed for some of that in the schedule.”

The Seattle Department of Transportation continues to make changes to the signal timing on either side of the Montlake Bridge to match real-time congestion. SDOT’s Jon Layzer knows it’s been a difficult month for residents.

“We still have a long way to go on this project and more impacts to come,” he said.

The Montlake Bridge will have to close for five more weekends this fall to work on the mechanical systems. That work is scheduled for weekends when the University of Washington football team is playing on the road.

The state has also removed 17,000 tons of contaminated soil from the old gas station at the Montlake interchange this month.

Check out more of Chris’ Chokepoints.

Chokepoints

Photo: Cars in traffic...

Nate Connors

Plan ahead as Revive I-5 could make it tough getting to Mariners games

This weekend, Revive I-5 between Seattle and Tukwila continues and crews prepare for long-term road closures in Shoreline.

14 hours ago

I-5 overpass 145th seattle...

Chris Sullivan

Sullivan: I-5 overpass at 145th Street to close, cause major disruptions

The North 145th Street overpass of I-5, right there at the new light rail station, is about to close for seven months.

23 hours ago

Photo: WSDOT crews pump concrete at new Veterans Drive tunnel....

Nate Connors

Late night I-5 closures coming up this week as WSDOT works on new tunnel

Contractors WSDOT are prepping for work on the new Veterans Drive Tunnel beneath I-5, adjacent to State Route 516.

2 days ago

Image: A Pierce Transit Stream Bus can be seen in Pierce County....

Micki Gamez

South Sound travelers may opt for transit after major service change

It's been seven years since Pierce Transit announced a major service change. The change means more access to Tacoma and the region.

3 days ago

headphones windshield obstructions...

Chris Sullivan

Sullivan: Driving with headphones, windshield obstructions in Washington

It's another episode of "rules of the road," I'm tackling two driving questions: Using headphones or windshield obstructions while driving.

3 days ago

four-way stops...

Chris Sullivan

Sullivan: Why do so many people get freaked out at four-way stops?

There is no mystery to how four-way stops work, so why do so many people mess up this simple maneuver?

8 days ago

Montlake neighborhood to be isolated for 520 construction this weekend