More delays for Bertha, viaduct project

May 18, 2015, 11:02 AM | Updated: 12:14 pm

A display at Monday’s Seattle City Council meeting shows the damage done to a drill on Bertha...

A display at Monday's Seattle City Council meeting shows the damage done to a drill on Bertha. (KIRO Radio/Josh Kerns)

(KIRO Radio/Josh Kerns)

Another tough break for Bertha. Further delays are expected for the giant tunnel machine and Seattle’s viaduct project.

The Washington State Department of Transportation told the Seattle City Council Monday that damage to Bertha will delay its progress further.

“Even though the damage is more than they were expecting to find, it’s not more than they were planning to repair at this point,” said Todd Trepanier with WSDOT.

For example, WSDOT said the outer seals and the steel retainers that hold them in place were destroyed. There was also damage to the cutter drive motor pinions and the main bearing bull gear.

Minor damage also occurred during disassembly.

Crews have also decided to replace the inner seals to make them more compatible with the new outer seals and main bearing. Those new seals have to be manufactured in Japan and won’t arrive until late May.

It is up to the Seattle Tunnel partners as to how long the project will be delayed.

So who’s going to pay for all this? WSDOT said STP and Hitachi are responsible for all aspects of the repair effort. WSDOT tells KIRO Radio’s Josh Kerns a dispute resolution is far down the road and it’s not a priority right now.

In addition to the damage, WSDOT told the City Council there are no simple answers as to why the ground near the SR 99 tunnel access pit settled about an inch last November.

One report, done by geotechnical firm Shannon & Wilson, Inc. and commissioned by WSDOT, said that dewatering related to tunneling machine repairs was the primary cause of the settlement.

A second report, concluded by Brierley Associates and commissioned by Seattle Tunnel Partners, said natural settlement and other dewatering activities are the primary reasons for the settlement, and tunnel-related dewatering only contributed in areas immediately surrounding the pit.

While the reports may differ slightly, they both conclude that settling related to dewatering has since stabilized, and ground movement was minor and caused no structural damage.

Richard D. Oxley contributed to this report

MyNorthwest News

america pnw food cities...

Jason Sutich

2 PNW cities crack top 5 of America’s best food cities

A new study ranked the cities with the best "foodie" culture, and two Pacific Northwest cities placed in the top five out of more than 180 U.S. cities.

7 hours ago

Sanctuary 1...

Julia Dallas

From saline pools to GLP-1s to halotherapy: Inside Seattle’s $8M Sanctuary

Glen Swain's $8 million Sanctuary will be a private performance, recovery, and social club.

9 hours ago

seattle earthquake port orchard...

Jason Sutich

4.2 magnitude earthquake hits near Port Orchard, felt from Issaquah to Olympia

A 4.2 magnitude earthquake hit near Wauna, Washington, Tuesday afternoon, with residents spanning from Issaquah to Olympia reporting that they felt the tremor.

11 hours ago

kitsap county sheriff doordash...

MyNorthwest Staff

Couple sentenced in stabbing, carjacking of DoorDash driver who offered their family a ride near Sequim

A couple accused of stabbing and carjacking DoorDash driver Melvin Swagerty after he stopped to help their family near Sequim last year are headed to prison.

12 hours ago

oregon wedding elk...

MyNorthwest Staff

VIDEO: Oregon wedding gets unexpected antlered guest

A wedding at Cannon Beach in Oregon was crashed by an unexpected guest.

13 hours ago

Bremerton SWAT dead...

Jason Sutich

Barricaded man fires several rounds at SWAT team, later found dead inside home near Bremerton

An armed man barricaded himself inside a home in unincorporated Bremerton on Monday and died from what appeared to be a self-inflicted gunshot wound.

13 hours ago

More delays for Bertha, viaduct project