MYNORTHWEST NEWS

‘Most prepared city in America’ continues to underestimates costs

Oct 12, 2015, 2:34 PM | Updated: Oct 13, 2015, 11:04 am

For $197 million, voters thought Seattle’s aging fire stations would be modernized, among oth...

For $197 million, voters thought Seattle's aging fire stations would be modernized, among other emergency-related projects. And who wouldn't with the levy motto: "Making Seattle the most prepared city in America." (AP)

(AP)

When voters approved a Seattle Fire levy in 2003 they thought they were really getting a bang for their buck.

For $197 million, voters thought Seattle’s aging fire stations would be modernized, among other emergency-related projects. And who wouldn’t with the levy motto, “Making Seattle the most prepared city in America.”

However, the lofty goal of upgrading the 33 fire houses has gone the way of the seawall. As reported in The Seattle Times, 32 of the fire houses came in over budget, and not just by a few thousand dollars here or there. Many of the projects went over budget by millions.

Take Fire Station 18 in Ballard, for example. Originally budgeted for $1 million, it has cost $6,610,000; 552 percent over budget, according to the Times.

The only station that was finished on budget was Fire Station 39 in Lake City. That was estimated at $5,758,000 and completed for $5,370,000.

All the added costs have turned the $197 million project into a $306 million project. On top of that, what was supposed to only take nine years is now in its 12th year.

The city argues that the reason for the higher costs is due to inflation in construction after the 2003 vote. Changing needs within the fire department have also led to increase the “scope” of some work, the Times reports.

This information follows the announcement that the Elliott Bay Seawall project’s budget increased. Originally budgeted at $300 million in 2013, project costs forced the city to increase spending on what it sees as one of the most critical infrastructure projects.

It’s not good news for a city that is asking voters to approve a nine-year $930 million transportation levy that it says will cover road improvement projects and bridge repair and future levies that are bound to follow. What’s even more concerning is Seattle Times’ Danny Westneat’s theory on why the fire projects are over budget. He writes that in order to get voter approval, the City Council cut $70 million from the original proposal of $260 million.

Westneat points out this is what happened with the seawall, too. The seawall was originally estimated to cost $390 million, but that cost dropped to $300 million. Now the cost is back up to about $400 million.

But voters can rest easy, because the city is looking into why the seawall is millions over budget. How? It is paying a consultant $200,000 to study the issue.

MyNorthwest News

Pierce County man sentenced child sex crimes...

Regan Gallo-Fenz

Pierce County man sentenced to 15 years in federal prison for child sex crimes

A Pierce County man has been sentenced to 15 years in federal prison after attempting to arrange the sexual abuse of children and producing child sexual abuse material, federal prosecutors announced.

3 hours ago

home listings...

Frank Lenzi

Home listings jump more than 25%: Is it a buyer’s market?

If you’re thinking about buying a house, now might be a good time: Home listings have risen, and pending sales have declined.

15 hours ago

Grays Harbor...

KIRO 7 News Staff

Grays Harbor deputies seek information about deadly hit-and-run near Satsop

The Grays Harbor County Sheriff’s Office is asking for the public’s help after a 53-year-old man was found dead along a road near Satsop last week.

15 hours ago

first responders...

Luke Duecy

Renton firefighter shot while responding to call highlights dangers facing first responders

A Renton firefighter was shot. The shooting is another example of the dangers first responders face while trying to help people in crisis.

16 hours ago

Macklemore (3)...

Julia Dallas

Macklemore says Climate Pledge Arena among venues that rejected his ‘Free Palestine Tour’

Macklemore said several venues, including Climate Pledge Arena, have rejected his efforts to bring his “Free Palestine Tour” to the U.S.

16 hours ago

work week...

Deedee Sun, KIRO 7 News

Tumwater to launch four-day work week in 2027

Some Tumwater city employees will soon be working a four-day week as part of a new plan the city hopes will improve the workplace.

17 hours ago

‘Most prepared city in America’ continues to underestimates costs