The City of Seattle is hiring a consultant to review why the Elliott Bay seawall project is one yea...

The City of Seattle is hiring a consultant to review why the Elliott Bay seawall project is one year behind schedule and millions over budget. (AP)

(AP)

The City of Seattle is hiring a private consultant to review its seawall replacement project that is now one year behind schedule and millions over budget.

The consultant will cost the city $200,000.

The consultant will investigate why the seawall along Elliott Bay will need an extra year and an additional $71 million dollars to get the job done. That’s in addition to the $339.2 million that the job was initially budgeted for.

Related: Cost of replacing Seattle’s seawall goes up

One reason for the delay and budget woe could be a decision made earlier in the project, according to KING 5 Reporter Chris Danniels.

“Because of a decision to create a temporary frozen wall to solidify the soil on the eastside of the project in the process to get rid of so-called grouting soils which have to be trucked offsite,” Daniels said. “That has caused the seawall project to balloon in costs, well above the $300 million voter-approved price tag.”

Seattle Mayor Ed Murray is also organizing a review panel of peer agency experts that includes public works directors and chief engineers to review the project. That is in addition to the private consultant.

The mayor’s office is looking at a few financing streams to cover the extra $71 million. He said those plans will not impact other departments or taxpayers.

KING 5 reports that options include: Commercial parking taxes, which could form a revenue stream for future large capital projects, such as streetcars and bridge replacements; real estate excise tax; waterfront parking revenue; or waterway funds from revenue from waterway-use permits.

MyNorthwest News

Puyallup...

Heather Bosch, KIRO 7 News

Witnesses recount heroic attempts to save man whose wheelchair got stuck on Puyallup train tracks

We’re learning more about the heroic efforts to try to free a man whose wheelchair became stuck on railroad tracks as a freight train approached.

19 minutes ago

Tacoma Narrows Bridge (2)...

Lexi Herda, KIRO 7 News

Expect major delays: Lanes closing on Tacoma Narrows Bridge for extensive repairs

Major lane closures are coming to the Tacoma Narrows Bridge, starting this weekend.

2 hours ago

seattle pilots world series...

Aaron Granillo

‘We’re all Brewers fans today’: Seattle’s link to the World Series

The former Seattle Pilots are in the World Series!

3 hours ago

tacoma police...

KIRO 7 News Staff

4th person arrested in death of Tacoma teen

A teenage boy was arrested Wednesday in connection with the death of a teen who was shot and killed in a Tacoma parking garage October 18.

3 hours ago

Sky Metalwala...

James Lynch

Nearly 15 years later, investigators still seek answers in toddler Sky Metalwala’s disappearance

As the anniversary of Sky Metalwala’s disappearance approaches, investigators are asking anyone who may have seen something to come forward.

4 hours ago

Halloween...

Paul Holden

Zombie walks, Museum of Fright, ‘Thriller’ and more kick off two weekends of Halloween fun around Seattle!

Halloween might be next weekend, but with all the fall fun going on, you’ll want to break out the costumes and start celebrating early!

4 hours ago

Seattle will dish out $200K to investigate overspending on seawall project