Bridge demolition plan ‘not being followed’ when Bonney Lake family was killed

Apr 16, 2015, 7:43 AM | Updated: 2:18 pm

Bonney Lake Mayor Neil Johnson said the contract for work on the SR 410 overpass expressly requires...

Bonney Lake Mayor Neil Johnson said the contract for work on the SR 410 overpass expressly requires the contractor to protect traffic from falling concrete and debris. (Photo courtesy Bonney Lake Police Dept.)

(Photo courtesy Bonney Lake Police Dept.)

Mayor of Bonney Lake Neil Johnson said the demolition plan of a Highway 410 bridge was not being followed when a slab of concrete crushed a family of three driving underneath.

“They weren’t even supposed to have started demolition yet,” Johnson told KIRO Radio’s Dori Monson.

At the same time crews were cutting the concrete on Monday, a meeting between the City of Bonney Lake and the contractor of the project was underway to update the city. Meetings between contractors of city projects and the city’s inspector occur every Monday, Johnson said.

“Nowhere in those meetings did they say we’re starting demolition,” Johnson told Dori. “They did not have anything in place for safety…”

Related: Pastor says Bonney Lake family was full of joy

The contract for the work expressly requires the contractor to protect traffic from falling concrete and debris. That includes placing flaggers on the roadway to stop traffic when demolition is occurring, Johnson said on the show. There also should have been proper equipment in place to prevent the concrete from falling.

“That’s how it should have worked,” Johnson said.

The subcontractor connected to the fatal accident previously committed a violation that led to the collapse of part of the Sauvie Island Bridge near Portland, The News Tribune reports. The 2008 collapse occurred because workers did not follow the demolition plan.

The work in Bonney Lake was part of a $1.7 million project to add lights and a sidewalk along Highway 410.

“The demolition plan calls for the bridge to be disassembled in pieces by saw cutting the concrete and rebar in sections, then removing the sections with hydraulic excavators,” the mayor said.

Johnson has ordered the Public Works Director to suspend work on the project.

Inspectors have found that the overpass is safe to travel over and under the work site. However, the westbound shoulder of the bridge is closed to pedestrian and other
traffic until further notice.

Josh and Vanessa Ellis and their 8-month-old son, Hudson, were killed in the accident.

The fatal accident is still being investigated.

A roadside memorial was placed near the site. A permanent memorial to remember the family could be built in the future, Johnson said.

KING 5 obtained a copy of the 911 recordings which include a call from one of the workers at the site.

“We just had a barrier rail fall on a freeway – I’m at a construction site right now. It fell off on a car,” he said.

“I’m sorry, what?” asked the dispatcher.

“I’m on a freeway job off of Angeline and 410 and the barrier rail that we’re working on fell off onto a car,” he said.

A witness was also heard describing the scene:

“Right underneath the Highway 410 bridge on Angeline, the whole thing caved in. And there’s a car in the roadway.”

The Associated Press contributed to this report.

Seattle News Archives & Features

SWAT standoff Kent (1)...

KIRO Newsradio staff

VIDEO: SWAT standoff in Kent after assault suspect barricades in home

There is a SWAT standoff happening at a home in Kent.

16 hours ago

Michelle Angstrom reacts to her burned down home and property after a wildfire hit the northwest pa...

Associated Press

Firefighters get a handle on Spokane wildfires as tens of thousands remain evacuated

SPOKANE, Wash. (AP) — Firefighters have taken advantage of cooler weather to begin getting a handle on wildfires that have displaced tens of thousands of people around Washington state’s second-largest city, but hotter, drier and breezier days lie ahead. Officials reported Wednesday that firefighters had established containment lines around the perimeters of all three fires […]

20 hours ago

Associated Press

Authorities arrest arson suspect in connection with one of Spokane’s devastating wildfires

SPOKANE, Wash. (AP) — A man from Spokane, Washington, was arrested Monday and charged with setting one of the devastating wildfires that have destroyed hundreds of homes and other structures in and around the state’s second-largest city. The Spokane County Sheriff’s Office said Aaron F. Farinacci, 37, was arrested and booked on suspicion of first […]

2 days ago

rain seafair aug. 1...

Tom Brock

Blue Angels cancel Saturday Seafair performance due to high winds

The U.S. Navy's precision flight team, the Blue Angels, had to cancel its Saturday performance at Seafair, due to high winds.

5 days ago

Washington Gov. Bob Ferguson has declared a statewide wildfire emergency. (Photo: WA. Dept. of Natu...

Tom Brock

Washington Gov. Bob Ferguson declares statewide wildfire emergency

Washington Governor Bob Ferguson declared a statewide wildfire emergency Saturday, which includes a prohibition on most outdoor and agricultural burning.

5 days ago

Associated Press

Seattle police say 15-year-old arrested in connection with festival shooting had a ghost gun

SEATTLE (AP) — The 15-year-old arrested after a shootout at food festival near Seattle’s Space Needle over the weekend was armed with an untraceable ghost gun with an extended magazine, police said Tuesday. Police Chief Shon Barnes told a news conference that the weapon was a 9 mm gun from Polymer80 — a now-defunct company […]

9 days ago

Bridge demolition plan ‘not being followed’ when Bonney Lake family was killed