Sound Transit releases new cost estimates for tunnel options to West Seattle and Ballard

Sep 12, 2019, 4:37 PM

sound transit...

Sound Transit says tunneling to West Seattle and Ballard will cost more. (KIRO 7 image)

(KIRO 7 image)

Sound Transit on Thursday released a new analysis showing light rail tunnels requested by community and political leaders would each add hundreds of millions of dollars to the cost of bringing train service to West Seattle and Ballard.

‘Stunning admission’ from Sound Transit during car tabs court case

The agency said tunneling beneath Pigeon Point in West Seattle would increase the cost by around $200 million. That’s on top of the $700 million more it would cost to also tunnel to the West Seattle Junction.

Tunneling to the Junction would also push the opening date for light rail beyond 2030, Sound Transit officials said.

The costs in the analysis compare to the representative alignment in the $54 billion Sound Transit 3 ballot measure that regional voters approved in 2016, which called for mostly elevated tracks to Ballard and West Seattle.

Concerned about the impact on neighborhoods of elevated tracks and trains delayed by a drawbridge over the Lake Washington Ship Canal, people in both Ballard and West Seattle have called for tunnels, although it’s not known where the extra money would come from.

In May, elected officials on the Sound Transit board advanced several alternatives for environmental review, including more expensive options that would require still-unidentified “third party funding.”

Agency officials say they would need a commitment for extra money by mid-2022 if Sound Transit is to stay on track opening light rail to West Seattle in 2030 and Ballard in 2035.

Sound Transit officials also did an initial assessment of an idea brought up during public comment for a station in the heart of Ballard, near 20th Avenue Northwest and Northwest Market Street, instead of on 14th Avenue or 15th Avenue Northwest and Market.

Agency staff members found that running a line over Burlington Northern Santa Fe tracks in Interbay and tunneling beneath Salmon Bay to 20th would cost an additional $750 million.

Sound Transit is gluing light rail tracks to I-90 floating bridge

They also looked at tunneling beneath Fishermen’s Terminal just north of the Ballard Bridge, which would require $450 million in extra money.

A tunnel to 14th Avenue or 15th Avenue would cost $350 million more than the ST3 representative alignment.

Agency officials say their analysis does not show more people would use a 20th Avenue station in the heart of the neighborhood because most riders would be transferring to buses anyway.

The agency also found that building double-elevated tracks in SoDo to reduce impacts on nearby businesses would add $300 million to the cost of the project and would require two major shutdowns of Central Link service during construction.

Sound Transit’s board of directors will decide in October whether to advance any of these ideas for environmental review, along with the concepts they agreed to study in May.

The analysis is expected to take through the end of 2020, with the board choosing a preferred alternative in 2021.

By Graham Johnson, KIRO 7

MyNorthwest News

Seattle retail theft court 3.2...

Regan Gallo-Fenz

2 men accused of stealing, reselling $3.2M in merchandise from online retailers face arraignment in Seattle

Two men accused running a retail theft scheme, fraudulently obtaining $3.2 million of stolen merchandise and refunds from retailers will be in Seattle court.

18 minutes ago

Lightrail shutdown Bellevue Seattle weekend...

Regan Gallo-Fenz

Seattle-Bellevue light rail riders face weekend shutdown

Sound Transit's 2 Line between Seattle and the Eastside will close this weekend for maintenance. Riders will need to use shuttle buses.

44 minutes ago

Speed zone cameras Pacific Alpac Elementary school...

Julie Berg, KIRO 7 News

New school speed zone cameras to begin 30-day warning period in Pacific

The City of Pacific says it has expanded its automated traffic safety camera program with the activation of new school speed zone cameras near Alpac Elementary School.

2 hours ago

Seattle Freeways tailgaters...

Charlie Harger

Harger: Turn signals, tailgaters, and the 5 most annoying drivers on Seattle freeways

I drive to work in the dark, and I’m coming down the ramp from westbound Highway 18 onto northbound I-5. Wipers going. Coffee in the cupholder. A semi is barreling down the right lane, and there’s a car in front of me on the ramp.

2 hours ago

seatac crash i-5...

KIRO 7 News Staff

NB lanes of I-5 in SeaTac reopen 7 hours after deadly multi-car crash

The northbound lanes of I-5 in SeaTac were closed for almost 7 hours, and traffic was backed up over a mile after a deadly multi-car crash on Thursday night.

3 hours ago

Wild Lanterns...

Paul Holden

Wild Lanterns, ski deals and tasty bites: Your Seattle area weekend guide

Wild Lanterns, ski deals, and tasty bites are just a few events going on this weekend around the Seattle area.

3 hours ago

Sound Transit releases new cost estimates for tunnel options to West Seattle and Ballard