Bertha could soon start spinning again beneath Seattle

Feb 9, 2015, 2:50 PM | Updated: Feb 10, 2015, 7:40 am

Crews have completed the concrete cradle that will hold Bertha the tunneling machine during repairs...

Crews have completed the concrete cradle that will hold Bertha the tunneling machine during repairs, WSDOT announced Monday. (WSDOT)

(WSDOT)

Bertha could soon start drilling again after more than a year idle beneath the Seattle waterfront. It won’t be far, but it’s a critical next step in the oft-delayed Seattle tunnel project.

The Washington Department of Transportation announced recently contractors have finished building the 120-foot access pit that will allow crews to reach the drill’s damaged cutter head.

Related: Seattle Tunnel Partners completes digging of Bertha repair pit

Plans call for the tunnel machine to dig through the 20-foot thick concrete wall at the bottom of the pit. Crews will then remove the 57-foot diameter cutting head and a massive crane will hoist it to the surface for repairs.

On Monday, WSDOT announced it had finished the concrete for a cradle at the bottom of the pit that will hold the drilling machine during the repairs.

“The next step is to tunnel through the concrete wall, per STP’s plans,” Alaskan Way Viaduct Replacement Program administrator Todd Trepanier says. “The length of time it takes Bertha to reach the pit will depend largely on her ability to mine through and digest the concrete. If she’s unable to mine through the wall, STP will create an opening from within the pit to give her an unobstructed path forward. Once inside the pit, crews will prepare the machine for disassembly and use the massive red gantry crane to hoist the front end of the machine to the surface for repairs.”

The world’s largest tunneling machine has been idle since it was damaged in December 2013.

Seattle Tunnel Partners, the contractor building the tunnel, won’t comment on its schedule and WSDOT says it can’t comment on the schedule until STP releases an update.

WSDOT tweeted Monday afternoon that the concrete cradle would need two days to cure, and preparations for drilling could begin soon after.

In STP’s last timeline released in November, it estimated Bertha would take four days to make her way through the wall into the access pit.

The schedule then estimated it would take approximately three months for the entire repair, and up to five months total to resume drilling on the tunnel.

As of now, STP still hopes to complete the tunnel by August of 2017.

MyNorthwest News

ICE Seattle Center shooting...

Jack Bilyeu, KIRO 7 News

KIRO 7 Exclusive: Video shows ICE arrest during Seattle Center mass shooting investigation

Footage obtained exclusively by KIRO 7 showed ICE arresting a man near Seattle Center Monday morning while the cleanup and investigation into Sunday night’s mass shooting was happening only feet away.

24 minutes ago

rabid bat renton gene coulon park...

KIRO 7 News Staff

Rabid bat found near playground at Renton’s Gene Coulon Park

Health officials are warning the public that a rabid bat was found near a popular park in Renton.

2 hours ago

power outage seattle thursday...

MyNorthwest Staff

Power outage affects more than 4,000 Seattle customers Thursday morning

More than 4,000 homes and businesses in Seattle are without power Thursday morning.

2 hours ago

sr 99 fatal crash lynnwood wsp...

MyNorthwest Staff

Fatal crash blocks southbound SR 99 near Lynnwood, no ETA for reopening

A fatal car crash has fully blocked southbound SR 99 early Thursday morning, the Washington State Patrol confirmed.

3 hours ago

Blue Angels...

Chris Sullivan

Want to catch the Blue Angels from a new angle? Hop on the light rail

The Blue Angels will take to the skies for Seafair, and for the first time, there will be light rail trains rolling across I-90.

3 hours ago

shon barnes katie wilson seattle police chief...

Frank Sumrall

Seattle Police Chief Shon Barnes fired by Mayor Katie Wilson

Shon Barnes was fired from his position as chief of the Seattle Police Department by Mayor Katie Wilson, multiple sources confirmed with KIRO Newsradio.

10 hours ago

Bertha could soon start spinning again beneath Seattle