Gov. Inslee astounded by Seattle tunnel contractor’s decisions to stop quality control

Jan 20, 2016, 8:50 AM | Updated: 12:56 pm

“We do already know that the contractor – for reasons that are just astounding to us &#...

"We do already know that the contractor - for reasons that are just astounding to us - stopped doing quality control work that they had been doing for the first thousand feet," Gov. Jay Inslee told Seattle's Morning News. (WSDOT)

(WSDOT)

The contractor responsible for operating the Seattle boring machine stopped doing quality control work sometime before a sinkhole opened up at the city’s waterfront.

Gov. Jay Inslee told Seattle’s Morning News that after the sinkhole opened behind Bertha Jan. 19, it became apparent that Seattle Tunnel Partners was not doing what it needed to in order to guarantee safety.

“We do already know that the contractor &#8211 for reasons that are just astounding to us &#8211 stopped doing quality control work that they had been doing for the first thousand feet,” Inslee said.

Related: Seattle considers cottage industry to ease housing, rent concerns

It was a comment that KIRO Radio’s Dave Ross wanted to make sure he heard correctly. The contractor stopped doing quality control work?

For the first 1,000 feet of work, crews with Seattle Tunnel Partners measured the amount of dirt being removed from the tunnel, Inslee explained. That helped prevent sinkholes, by making sure there wasn’t a “void.” But for reasons Inlsee couldn’t explain, they stopped doing that work.

“We are very disappointed that the contractor failed in that regard,” Inslee added.

Inslee ordered the work involving Bertha stopped. The contractor now has to complete a root-cause analysis of how and why the sinkhole appeared and how crews will prevent it from happening again. Inslee hopes this will be done as “soon as humanly possible,” because the project is already two years behind schedule.

“This thing is going underneath the viaduct, and we know how fragile that is,” Inslee said. “Everyone knows a sinkhole under the viaduct could be catastrophic and we cannot have that risk without being assured that they’re going to preform quality control necessary to prevent that from happening again.”

Why not just stop Bertha, before it does some real damage?

It comes down to the money already invested in the project, Inslee explained.

“To throw money overboard and waste it does not seem [reasonable],” he said.

Inslee said the project still has a “reasonable chance of success.”

MyNorthwest News

seattle mayor katie wilson budget deficit billion...

MyNorthwest Staff

Public hearing taking place Tuesday for Seattle residents to comment on Katie Wilson’s budget proposal

A public hearing is happening Tuesday on Seattle Mayor Katie Wilson’s proposed two-year budget.

2 hours ago

A Seattle Police Department vehicle can be seen on Aurora Avenue North in Seattle. (Photo courtesy ...

MyNorthwest Staff

Early-morning shooting at Aurora Avenue gas station injures delivery driver

The Seattle Police Department is investigating a shooting at a North Seattle gas station. Gunfire erupted around 4:45 a.m. Tuesday morning on Aurora Avenue N.

2 hours ago

equifax settlement credit scores...

KIRO 7 News Staff

Equifax agrees to proposed $100 million settlement over credit score errors

Equifax has agreed to a proposed $100 million settlement to resolve a class-action lawsuit alleging the credit reporting company provided inaccurate credit scores to millions of consumers.

2 hours ago

clark county deputy dui stabbing...

KIRO 7 News Staff

Clark County deputy accused of stabbing DUI suspect to death will not be charged; deemed ‘justified’

A Clark County Sheriff’s Office deputy accused of stabbing a DUI suspect to death last year will not be charged, according to the prosecutor’s office.

3 hours ago

WSF Washington State Ferries...

Luke Duecy

Washington State Ferries still face lingering disruptions after 23 engineers call out sick

Washington State Ferries is dealing with lingering disruptions Tuesday after 23 engine-room employees called in sick Monday, leaving 13 of the system’s 18 vessels out of service.

3 hours ago

Revive I-5 (1)...

Chris Sullivan

Northbound Revive I-5 enters final stretch as key on-ramp prepares to reopen

South Lake Union and Capitol Hill drivers are about to get their northbound I-5 access back, as the state pushes toward the end of Revive I-5.

4 hours ago

Gov. Inslee astounded by Seattle tunnel contractor’s decisions to stop quality control