A timeline of key dates in Seattle Tunnel Project:

January 2008 – Washington Gov. Christine Gregoire announces state will take down Alaskan Way Viaduct in 2012.

January 2009 – State of Washington, King County, city of Seattle and Port of Seattle announce agreement to replace Alaskan Way Viaduct with bored underground tunnel

May, 2009 – Governor Christine Gregoire signs measure authorizing $2.8 billion in state funds for tunnel project.

April, 2013 – The world’s largest tunneling machine, now christened “Bertha”, arrives in Seattle.

July 30, 2013 – Bertha begins drilling. Initial plans call for drilling to take 14 months.

July-December, 2013 – Bertha travels 9.270 feet of planned 9,270 feet.

December 3, 2013 – Bertha strikes 8-inch-diameter steel pipe after tunneling 59 feet.

December 6, 2013 – Bertha components shut down during attempts to drill at high power. Drilling halted.

December 7, 2013 – Seattle Tunnel Partners operators try to get Bertha moving again. Drill running at elevated temperatures. Drilling remains stopped.

January 3, 2014 – WSDOT reveals steel pipe to blame for tunnel stoppage.

January 25, 2014 – Seattle Times reports steel pipe struck by Bertha was put there by WSDOT engineers to study groundwater and included in plans provided contractor prior to tunnel bid submission.

January 28-29, 2014 – Bertha drills two feet each day as STP restarts drill and tries to determine cause of overheating problems. Drilling halted again.

February 7, 2014 – WSDOT announces Bertha seals and bearing damaged, likely causing overheating problems, no schedule for repairs or resumption of drilling.

February 28, 2014 – Seattle Tunnel Partner project director Chris Dixon says contractor hopes to complete repairs and resume drilling by September 1.

March 2014 – STP continues working with Bertha manufacturer to determine best way to repair drill and resume operations. Plans call for 120-foot-deep pit ahead of drilling machine to facilitate repairs. WSDOT digs 60 narrow test holes to check for historic artifacts ahead of repairs.

April 9, 2014 – Seattle tunnel critic files lawsuit to stop repairs on Bertha.

April 21, 2014 – WSDOT, STP announce tunneling will not resume until March 2015.

MyNorthwest News

dead whale cruise ship alaska...

KIRO Newsradio staff

‘Tremendously sad’: Dead fin whale found on bow of cruise ship near Sitka, Alaska

A dead fin whale wound up on the bow of the Norwegian Joy cruise ship and has blocked its port near Sitka Bay in Alaska.

47 minutes ago

airport baggage claim sign...

Michael Strite

SEA leaps 6 spots in airport satisfaction study after year of major upgrades

Seattle-Tacoma International Airport ranks 11th out of 20 United States airports in customer satisfaction.

2 hours ago

Mountlake terrace arrest...

Jason Sutich

Mountlake Terrace police arrest man accused of unsolicited contact with women, girls in at least 12 incidents

Mountlake Terrace police arrested a man accused of several instances where he allegedly approached juvenile and adult women and initiated unsolicited contact.

3 hours ago

stevens county earthquake...

MyNorthwest Staff

4.2 magnitude earthquake near Nelson, B.C. felt as far south as Stevens County

A 4.2 magnitude earthquake hit near Nelson, British Columbia, early Thursday morning, with residents in eastern Washington reporting they felt the tremor.

3 hours ago

capitol hill chicken restaurant...

MyNorthwest Staff

Seattle food influencer with 7 million followers opening chicken restaurant on Capitol Hill

A Seattle-based food influencer and chef with more than 7 million social media followers is opening a chicken restaurant on Capitol Hill.

5 hours ago

thurston county deputy fired...

Jason Sutich

Thurston County deputy fired after domestic violence victim he failed to investigate went missing two days later

A Thurston County Sheriff's Office deputy was terminated after failing to investigate a domestic violence incident and misrepresenting material information.

6 hours ago

A Bertha timeline: From conception to today