520 bridge project may go another $128 million over budget

Aug 26, 2013, 2:42 PM | Updated: 3:10 pm

State officials say construction delays and redesign costs could use up the Highway 520 bridge&#821...

State officials say construction delays and redesign costs could use up the Highway 520 bridge's $100 million in reserves and eventually send the project another $128 million into the red. (AP Photo/file)

(AP Photo/file)

Taken from Monday’s edition of The Dori Monson Show.

State officials say construction delays and redesign costs could use up the Highway 520 bridge’s $100 million in reserves and eventually send the project another $128 million into the red.

The news of the $128 million more in overruns was released on the WSDOT website on Friday. That’s when you dump bad news because they hope and pray that everybody in the media will forget about the story by the time Monday rolls around.

Sorry WSDOT, I remembered.

I also remembered there’s a huge transportation funding package that they want to put to the voters this fall. Who is going to get that money? The department of transportation that cannot come close to making budget.

They are going to be billions over on the 520 bridge. They are going to be billions over on the downtown Seattle tunnel. Their solution is, let’s get more money. Give us more money so we can improve transportation.

How about you figure out how to spend what you’ve already got?

What is remarkable about this revelation by the WSDOT on Friday is that just last month they held a news conference saying this wasn’t going to happen again.

“WSDOT has acknowledged responsibility for the pontoon design error that led to the repairs we are performing now, and the agency has taken major steps to ensure these types of issues are not repeated,” said new Transportation Secretary Lynn Peterson.

The state reportedly doesn’t have concrete plans for finding more money if the project requires it.

How can we trust them with a gigantic multi-billion dollar transportation package that they’re asking for this fall, when they cannot do the projects that are on the table now without running billions over?

Why am I the only one asking these questions about them? It’s unbelievable to me.

Taken from Monday’s edition of The Dori Monson Show.

The Associated Press contributed to this report.

Related:
520 bridge design errors add up costs, delays

JS

MyNorthwest News

king county courthouse security...

Frank Lenzi

King County courthouse logs more than 50 security reports in 2026, including judge assault

More than 50 security incident reports have been filed at the King County Courthouse so far in 2026, including an assault on a judge in their courtroom.

4 minutes ago

surveillance camera...

Julia Dallas

Wilson turns stadium district cameras back on, authorizes SPD expansion

Seattle Mayor Wilson announced she is turning on the stadium district cameras immediately and allowing the SPD to expand its camera network.

58 minutes ago

I-001 parents bill of rights...

Frank Sumrall

Parents’ bill of rights initiative I-001 fails to pass

Initial results show Initiative 001 narrowly trailing, with 52.77% of votes counted opposed and 47.23% in favor. The measure seeks to restore the original 2024 parents’ bill of rights by undoing changes made by the Washington Legislature last year.

1 hour ago

cle elum arrest dead...

KIRO 7 News Staff

15-year-old found dead during Cle Elum arrest operation

A 15-year-old boy was found dead inside a Cle Elum-area home Monday after deputies attempted to serve an arrest warrant.

2 hours ago

seattle paramount oh mary record...

Manda Factor

‘Oh, Mary!’ sets $2.5 million box office record at Seattle’s Paramount Theatre

The production of “Oh, Mary!” grossed more than $2.5 million in Seattle, setting a record for the highest-grossing week for a play at the Paramount Theatre.

2 hours ago

Seattle fall out boy tour...

Julie Berg, KIRO 7

Fall Out Boy announces 2027 Seattle stop for Twilight of the Punks Tour

The Seattle Mariners announced Monday that Fall Out Boy will bring their Twilight of the Punks North America Stadium Tour to T-Mobile Park on Aug. 24, 2027.

3 hours ago

520 bridge project may go another $128 million over budget