Concrete strike’s impact on West Seattle Bridge timeline unclear as SDOT makes final pours

May 24, 2022, 3:50 PM

west seattle bridge...

The West Seattle Bridge (Sounder Bruce via Flickr)

(Sounder Bruce via Flickr)

The Seattle Department of Transportation (SDOT) still hopes to open the West Seattle Bridge in “mid-2022,” according to a spokesperson with the transportation agency. A to-be-announced, updated timeline will be delivered on June 9.

“Our construction contractor is planning to finish the final structural concrete pours this week, marking the end of a challenging process that has affected our reopening schedule,” SDOT’s Ethan Bergerson wrote to MyNorthwest.

SDOT contracts with Kraemer North America for the West Seattle Bridge. A Kraemer spokesperson declined to comment on whether the reopening would be pushed beyond that mid-2022 timeframe.

“Some delays have been associated with the concrete strike earlier in the year. Those after-effects continue. And then you’ve got just some normal supply chain issues that have been created in this post-pandemic world.”

Kraemer declined to elaborate on what those supply-chain issues entailed.

Cadman – Lehigh Hanson is the primary concrete supplier for the repair project. A shop steward with the supplier alleges that Kraemer was not ready to receive the specialized concrete required for structural pours after the Teamsters’ strike lines broke March 15, and some deliveries to the West Seattle Bridge resumed April 5.

Employers deny claims of collusion, price-fixing as Seattle-area concrete strike nears fifth month

“I was the first truck that was out to that job site when we came back from strike … We did expansion joints, which is not part of the structural part of the bridge … The first time they actually did any structural concrete to that bridge was April 16,” the Cadman shop steward told MyNorthwest.

In February, civic leaders, including Seattle Mayor Bruce Harrell, King County Executive Dow Constantine, and Sound Transit CEO Peter Rogoff made a press appearance in which they called on the Teamsters and suppliers to reach an agreement before Feb. 20, otherwise critical infrastructure repair, including the West Seattle Bridge, would run the risk of delays.

“When they said that they needed concrete, and they were ready Feb. 19 [Feb. 20], that was a flat-out lie,” the shop steward noted, referencing the timeline put forth by Mayor Harrell and company.

Kraemer calls that allegation “neither true nor accurate.”

“We pour all the time. So there are elements that were ready when mid-April was around. And some elements are yet to be formed,” the spokesperson for Kraemer added. They noted that, specifically, post-tensioning on the north girder was ready for concrete when Cadman ended their strike.

After this week’s final structural concrete pours, there is a review of post-tensioning work completed to make any real-time adjustments needed.

MyNorthwest News

flight...

KIRO 7 News Staff

What are your options if your flight is delayed or canceled due to the FAA ground stop?

What are your options if you’re flying out today and your flight was canceled or delayed?

1 hour ago

2 Costco...

MyNorthwest Staff

Largest Costco gas station now open in WA

Costco’s largest gas station is now open in Issaquah.

2 hours ago

microsoft outage...

Luke Duecy

The Spin: Microsoft outage and how the company used PR to manage a global service disruption

A major Microsoft outage disrupted Outlook, Teams, Copilot, and other Microsoft 365 services for two days.

2 hours ago

Camas School District U.S. Department of Education Investigation Transgender sports...

Regan Gallo-Fenz

US Education Dept. launches investigation into Camas School District over Title IX allegations

The U.S. Department of Education launched an investigation into the Camas School District to determine violated Title IX.

3 hours ago

wa college students career...

Luke Duecy

WA colleges deliver strong return on investment, but career guidance falls short, report finds

A new report finds universities aren't doing enough to help students turn their degrees into successful careers.

5 hours ago

3 ground stop...

Julia Dallas

Ground stop lifted as hundreds of flights canceled at SEA; officials cite ‘major engineering defect’

A ground stop has been issued for all airports nationwide by the Federal Aviation Administration (FAA).

5 hours ago

Concrete strike’s impact on West Seattle Bridge timeline unclear as SDOT makes final pours