There will be no quick or easy fix for the broken tunneling machine under Seattle. The Washington State Department of Transportation now says it will be months before Bertha starts drilling again.

Seattle Tunnel Partners is working with Hitachi Zosen, the machine’s manufacturer, to determine how best to fix the broken seals surrounding the main bearing of the boring machine. They say it could be another six or seven months before the giant drill starts churning under Seattle.

The state is weighing several options on how to fix the broken seals that lubricate and protect the main bearing that powers the cutterhead. The Seattle Times reports the state might have to dig a pit 115 feet deep in front of the drill to remove the 630 ton cutter-head to replace the seals.

The contractor says the state could also take apart the drill from the rear and reach the seal that way. Depending on what inspections this week show, the contractor might be able to deliver the parts through the back of the machine.

Either way, it will be months before drilling resumes.
Engineers still don’t know why the seals on the $80 million machine failed.

The machine has been mostly idle for two months and is only one-tenth of the way toward completing a 1.7-mile tunnel.

The project is budgeted at $1.4 billion. The total viaduct replacement is estimated to be a $3.1 billion project. The tunnel project is supposed to be finished in late 2015.

The Associated Press contributed to this report.

MyNorthwest News

_spokane wildfires...

Luke Duecy

Convicted felon arrested in connection with Old Trails Fire in Spokane

Governor Bob Ferguson said federal resources are on the way to help Washington battle 17 major wildfires burning more than 260,000 acres.

8 hours ago

pierce transit (1)...

Nate Connors

Chill out during this week’s heat wave courtesy of Pierce Transit

It's become a regular service to Pierce County residents during the excessive heat bursts we often get throughout our summer season.

10 hours ago

Gifford Pinchot National Forest (1)...

Julia Dallas

Gifford Pinchot National Forest issues emergency closures for wildfire

The Gifford Pinchot National Forest has issued an emergency closure order for the High Lava Fire.

11 hours ago

washington...

James Lynch

Crime drops across every major category in Washington, but officials warn the full picture is more complicated

Crime declined across every major category in Washington in 2025, with sharp drops in murders, violent crime, and property crime.

11 hours ago

seattle homelessness...

Frank Lenzi

Seattle, King County plan to reclaim nearly $160M in homelessness contracts from KCRHA

The King County Regional Homelessness Authority (KCRHA) will survive despite calls from some Seattle and King County leaders to dissolve it.

12 hours ago

King County Metro...

KIRO 7 News Staff

King County Metro to add 9 new bus routes and 3,000 additional weekly bus trips to schedule

King County Metro is adding nine new bus routes and more than 3,000 additional weekly bus trips to its schedule.

12 hours ago

Bertha not expected to move for months as tunnel workers attempt to fix machine