Progress on the Seattle tunnel project has reached another milestone.

The Washington State Department of Transportation reports that Bertha the boring machine reached the halfway mark on Friday after tunneling past Pike Place Market.

Seattle Tunnel Partners, the contractor, has now excavated more than 4,600 feet of the 9,270-foot tunnel.

Related: Has the perception of Bertha and the Seattle Tunnel project changed?

Much of the progress Bertha has made occurred during the past five months. The contractor has excavated more than 3,000 feet since leaving the planned maintenance stop on April 29 and going underneath the Alaskan Way Viaduct.

Bertha is now under First Avenue, between Pike and Pine streets. Mining will continue for a short time before another planned stop is made for approximately one month.

“Bertha has been steadily on the move and made her way to the second half of the tunnel,” Gov. Jay Inslee said. “This is good progress and I appreciate everyone’s focus on making sure we safely complete this project.”

The finish line is a 90-foot deep pit near Thomas Street.

The most recent schedule from the contractor shows that tunneling will end in the summer of 2017. Based on the contractor’s schedule, the state estimates the tunnel could be open to traffic by early 2019.

MyNorthwest News

copper wire thieves ballard...

MyNorthwest Staff

Copper wire thieves hit Ballard businesses repeatedly, owners demand action

Copper wire thieves are hitting Ballard businesses hard, leaving owners with repair bills worth thousands of dollars.

10 minutes ago

seattle police interim chief katie wilson...

Nia Bliss, KIRO 7 News

Seattle Police Officers Guild praises interim chief appointment while criticizing mayor’s actions

Seattle Mayor Katie Wilson announced the appointment of Deputy Chief Andre Sayles to the Interim Chief role effective Friday.

51 minutes ago

wa electricity bill PSE...

MyNorthwest Staff

Washington AG Nick Brown fights back against PSE’s proposed 29% electric, 20% gas rate hikes

Washington Attorney General Nick Brown is pushing back against proposed utility rate hikes from Puget Sound Energy (PSE).

1 hour ago

Mariners jimothy seattle...

Jason Sutich

Due to high demand, second ‘Jimothy Night’ for Seattle Mariners coming in August

The Seattle Mariners are hosting a second "Jimothy Night" next month after the first day themed around the celebrity raccoon sold out.

2 hours ago

level 3 evacuation chelan county fire...

KIRO 7 News Staff

Level 3 evacuation orders issued for areas of Entiat Valley of Chelan County for Little Giant Fire

Level 3 ‘Go Now’ evacuation orders have been issued for an area in Chelan County impacted by the Little Giant Fire.

3 hours ago

Seafair...

Paul Holden

Seafair weekend is here — but so are a lot more events around the Seattle area!

July is coming to a close, and that means that the countdown is on to get all those things on your summer bucket list crossed off!

4 hours ago

Bertha reaches halfway point in tunnel project