Bertha reaches halfway point in tunnel project

Oct 3, 2016, 7:44 AM | Updated: 8:50 am

Progress on the Seattle tunnel project has reached another milestone.

The Washington State Department of Transportation reports that Bertha the boring machine reached the halfway mark on Friday after tunneling past Pike Place Market.

Seattle Tunnel Partners, the contractor, has now excavated more than 4,600 feet of the 9,270-foot tunnel.

Related: Has the perception of Bertha and the Seattle Tunnel project changed?

Much of the progress Bertha has made occurred during the past five months. The contractor has excavated more than 3,000 feet since leaving the planned maintenance stop on April 29 and going underneath the Alaskan Way Viaduct.

Bertha is now under First Avenue, between Pike and Pine streets. Mining will continue for a short time before another planned stop is made for approximately one month.

“Bertha has been steadily on the move and made her way to the second half of the tunnel,” Gov. Jay Inslee said. “This is good progress and I appreciate everyone’s focus on making sure we safely complete this project.”

The finish line is a 90-foot deep pit near Thomas Street.

The most recent schedule from the contractor shows that tunneling will end in the summer of 2017. Based on the contractor’s schedule, the state estimates the tunnel could be open to traffic by early 2019.

MyNorthwest News

seattle diner restaurant best...

Jason Sutich

Japanese-inspired Seattle diner named among best new restaurants of 2026

The Wayland Mill, an American diner in North Lake Union, earned national recognition when Bon Appétit ranked it among the best new restaurants of 2026.

1 hour ago

dead whale commencement bay...

Eric Thomas, KIRO 7 News

Scientists work to identify cause of death for a whale at Commencement Bay

A dead whale was found decaying in Commencement Bay on Monday. Scientists are trying to figure out how it died.

4 hours ago

USS Abraham Lincoln bremerton middle east...

MyNorthwest staff with wire reports

USS Abraham Lincoln could be headed to Bremerton after record-setting Middle East deployment

The USS Abraham Lincoln, a Navy aircraft carrier with strong ties to the Puget Sound, could be headed for Bremerton.

4 hours ago

lakewood 2-month-old son prison...

Jake Chapman, KIRO 7 News

Lakewood man sentenced to 34 years in prison for death of 2-month-old son

A Lakewood man was sentenced to 34 years in prison after pleading guilty to the murder of his two-month-old son.

5 hours ago

2 slow moving vehicle law...

Chris Sullivan

Five cars behind you and going under the speed limit? In WA, you’re breaking the law

You might know the speed limit, but do you know you're breaking the law if you're driving under it with five cars stuck behind you?

6 hours ago

trump lake ontario lake america...

Associated Press

Trump says he’s considering renaming Lake Ontario as ‘Lake America’ as trade war escalates

President Donald Trump said Tuesday that he is considering changing the name of Lake Ontario to “Lake America” as the trade war between the United States and Canada intensifies.

7 hours ago

Bertha reaches halfway point in tunnel project