Lane reductions over Tiger Mountain to last two months

Feb 8, 2024, 8:18 AM | Updated: 9:58 am

The next phase of the State Route 18 Widening Project is underway and expected to last into April. Work will be done late at night to avoid disrupting peak travel times.

“We’ve got about a couple months worth of lane reductions coming to overnight,” Washington Department of Transportation (WSDOT) spokesperson Marcus Humberg said. “The whole point of this closure is to really kind of move on to three bridges we’re building here.”

WSDOT reported it has already built a four-lane bridge across Lake Creek, one across Raging River and one over Deep Creek.

“They need to put in some pilings alongside the road. And that’s going to require a lane reduction for the construction vehicles that are on the road to do that actual work,” Humberg explained. “And given there are only two lanes in that area, we’re going to have to take one lane for construction that leaves one lane for traffic, and that traffic will have to alternate east and westbound. One at a time with a pilot car kind of guiding everybody through the construction zone.”

Sullivan: Tire ban, $1,000 fines for idling have life in state Legislature

Humberg added that drivers can expect up to 20-minute delays between Deep Creek and Lake Creek, which is a mile-and-a-half apart. Closures are Sunday through Thursday, between 9 p.m. and 5 a.m.

According to Bob Van Horn, assistant project engineer with WSDOT, this project has another year before total completion.

“I think they really want to get traffic on them by early 2025. But that’s up in the air. There are a lot of things that have to happen between now and then to get that going. But when we do get traffic on the new bridges, there’s still some work to do below the bridges in the creek.”

Right now, the project is on schedule, according to Van Horn.

“So the work that’s been going on specifically has kind of been going in phases,” Humberg said. “They started just south of the intersection at I-90 and built a four-lane bridge across Deep Creek, and then they’ve been pushing the widening down toward the bridge at Raging River. So it’s kind of these bridges that are that essential piece that links everything together.”

Sputtering out: Push for state gas price transparency fails in legislature

Humberg explained that as workers are building the bridges, they are widening the lanes.

“We know that there’s been a lot of traffic, there’s been several incidents on that freeway, up and over SR 18. And we’ve been taking a lot of steps to try and protect the public, we’ve reduced speed limits in the area,” Humberg said. “You’ve got to give yourself enough time, you’ve got to give the construction workers some patience, you got to follow those posted speed limits and really slow down in the construction zones.”

This project is vital to alleviate the growing traffic volumes. Recent numbers show there are roughly 28,000 daily commuters over Tiger Mountain.

MyNorthwest News

longview plant...

Julia Dallas

35 violations found at Longview plant following tank rupture that killed 11 workers

Three months after a tank rupture killed 11 workers at a Longview plant, Ecology has found 35 environmental violations at the facility.

11 hours ago

polar bear...

KIRO 7 News Staff

Point Defiance Zoo’s polar bear is leaving Tacoma

Point Defiance Zoo & Aquarium’s 5-year-old polar bear, Laerke, is moving.

12 hours ago

Bite of Seattle (4)...

Tyrah Majors, KIRO 7 News

One month after Bite of Seattle shooting, King County expands mobile crisis response efforts

One month after a deadly shooting at the Bite of Seattle, investigators are still working to identify a possible third shooter connected to the gunfire.

13 hours ago

Kirkland stolen property...

Jason Sutich

Kirkland police recover more than $30K in stolen property across King County

More than $30,000 in stolen property connected to burglaries and vehicle prowls was recently recovered across several King County cities.

13 hours ago

speed cameras vandalized...

James Lynch

Vandals target Bellevue’s new speed cameras

Just weeks after new speed cameras went up, the Bellevue Police Department said vandals have already started targeting them.

14 hours ago

Seattle fatal collision motorcycle...

MyNorthwest Staff

Motorcyclist killed in fatal hit-and-run collision near Seattle Pacific University

A fatal collision blocked all lanes near 6th Avenue W and W Nickerson Street on Wednesday, and Seattle police are currently investigating the cause.

15 hours ago

Lane reductions over Tiger Mountain to last two months