More delays for Bertha, viaduct project

May 18, 2015, 11:02 AM | Updated: 12:14 pm

A display at Monday’s Seattle City Council meeting shows the damage done to a drill on Bertha...

A display at Monday's Seattle City Council meeting shows the damage done to a drill on Bertha. (KIRO Radio/Josh Kerns)

(KIRO Radio/Josh Kerns)

Another tough break for Bertha. Further delays are expected for the giant tunnel machine and Seattle’s viaduct project.

The Washington State Department of Transportation told the Seattle City Council Monday that damage to Bertha will delay its progress further.

“Even though the damage is more than they were expecting to find, it’s not more than they were planning to repair at this point,” said Todd Trepanier with WSDOT.

For example, WSDOT said the outer seals and the steel retainers that hold them in place were destroyed. There was also damage to the cutter drive motor pinions and the main bearing bull gear.

Minor damage also occurred during disassembly.

Crews have also decided to replace the inner seals to make them more compatible with the new outer seals and main bearing. Those new seals have to be manufactured in Japan and won’t arrive until late May.

It is up to the Seattle Tunnel partners as to how long the project will be delayed.

So who’s going to pay for all this? WSDOT said STP and Hitachi are responsible for all aspects of the repair effort. WSDOT tells KIRO Radio’s Josh Kerns a dispute resolution is far down the road and it’s not a priority right now.

In addition to the damage, WSDOT told the City Council there are no simple answers as to why the ground near the SR 99 tunnel access pit settled about an inch last November.

One report, done by geotechnical firm Shannon & Wilson, Inc. and commissioned by WSDOT, said that dewatering related to tunneling machine repairs was the primary cause of the settlement.

A second report, concluded by Brierley Associates and commissioned by Seattle Tunnel Partners, said natural settlement and other dewatering activities are the primary reasons for the settlement, and tunnel-related dewatering only contributed in areas immediately surrounding the pit.

While the reports may differ slightly, they both conclude that settling related to dewatering has since stabilized, and ground movement was minor and caused no structural damage.

Richard D. Oxley contributed to this report

MyNorthwest News

winco foods grocery store seattle renton opening...

Jason Sutich

New WinCo Foods coming to Renton’s former Fry’s Electronics space

WinCo Foods is opening up its newest grocery store location in Renton at The Landing, inside the former Fry's Electronics building.

23 minutes ago

car crash everett 100 mph...

KIRO 7 News Staff

Car crashes into Everett neighborhood at 100+ mph after brief pursuit, at least 1 seriously injured

At least one person was seriously injured after a car crashed into an Everett neighborhood and landed upside-down in a front yard early Wednesday morning.

57 minutes ago

bill gates foundation jeffrey epstein...

Luke Duecy

Bill Gates ignored repeated warnings about Jeffrey Epstein, independent Gates Foundation review finds

Bill Gates was repeatedly warned by employees about the reputational risks of associating with convicted sex offender Jeffrey Epstein, but continued meeting with him for years.

1 hour ago

amber alert kennewick kidnap...

Frank Sumrall

Amber Alert suspect surrenders after kidnapping 4-year-old daughter in Kennewick

After a week on the run, Amber Alert suspect Matthew Susmilch has surrendered himself to authorities.

2 hours ago

missing vulnerable person kent...

Frank Sumrall

Kent police searching for vulnerable adult missing since July 12

The Kent Police Department issued a "missing vulnerable adult" alert after a resident went missing in early July.

3 hours ago

fire seattle warehouse investigators...

Lexi Herda, KIRO 7 News

Investigators say fire that destroyed Seattle warehouse was set on purpose

Investigators determined that a fire that destroyed a warehouse in Seattle’s Industrial District was intentionally set.

3 hours ago

More delays for Bertha, viaduct project