MYNORTHWEST NEWS

Steel shortage derailing plans to complete ‘Revive I-5′ project

Aug 2, 2021, 6:27 AM | Updated: 11:22 am

Seattle I-5, steel, revive...

Cars on I-5 southbound, headed toward downtown Seattle in July 2021. (MyNorthwest photo)

(MyNorthwest photo)

A steel shortage is derailing plans to complete the massive “Revive I-5” project in Seattle.

The Washington State Department of Transportation said pavement repairs from southbound I-5 between I-90 and Spokane Street are on schedule, but a lack of steel could push back the completion date of another part of the two-year project.

A major component of the $25.6 billion project is installing more than 50 expansion joints.

“Expansion joints allow the freeway to expand and contract with heat, cold, and heavy-duty traffic,” said Tom Pearce of WSDOT.

So far, crews have yet to replace even one.

“Our contractor is having a little bit of an issue procuring steel for this,” Pearce said. “It’s probably going to be late August, early September before they can get the steel that they need.”

So, how does that impact your drive on I-5?

According to WSDOT, there will not be weekend morning lane reductions for at least a few weeks. So far, only two of 16 planned weekend closures have happened.

Revive I-5 returns to Seattle with a full freeway closure

“This year, we’re hoping to get as many weekends in as possible,” Pearce said.

Pearce says as soon as the contractor gets the needed steel, crews will begin installing a few expansion joints at a time.

“It’s a big undertaking to replace these expansion joints because we have to reduce the freeway down to one or two lanes,” Pearce said.

In the meantime, pavement repairs will continue.

MyNorthwest News

light rail stabbing pioneer square...

Frank Lenzi

Stabbing victim boards Sound Transit light rail train in Seattle’s Pioneer Square

A person was stabbed in Seattle's Pioneer Square neighborhood late Sunday afternoon and then boarded a northbound Sound Transit light rail train before first responders could intervene, the agency said.

8 hours ago

Andre Sayles (2) bite of seattle shooting suspect...

Tom Brock

Texts on hold: SPD delays Bite of Seattle shooting records

Interim Seattle Police Chief Andre Sayles says he needs more time before he can release the police department's internal communications the night of the deadly "Bite of Seattle" shootings.

13 hours ago

A Coast Guard rescue helicopter lifts an injured hiker to safety from Oregon's Three Sisters Wilder...

Tom Brock

Hoist in the high Cascades: Coast Guard lifts injured hiker from treacherous Oregon mountaintop

A Coast Guard helicopter crew rescued an injured hiker from treacherous conditions in the mountains of central Oregon last week.

15 hours ago

Two alleged wire thieves caught in the act on Highway 12 near Aberdeen. Authorities estimate they d...

Tom Brock

Grounded: Grays Harbor deputies cut short highway wire heist

Deputies in Grays Harbor arrested two men Saturday for trying to steal hundreds of feet of wire along Highway 12.

16 hours ago

Mount Rainier...

425

Why interest in this Mount Rainier-sighting app is surging

A community-driven app that tracks Mount Rainier’s visibility is gaining attention.

21 hours ago

Katie Wilson (8)...

Luke Duecy

The Spin: How Seattle Mayor Katie Wilson’s team communicates after gun violence

Four deadly shootings in a little more than a month, including the Bite of Seattle shooting and three fatal shootings in Belltown, provide a backdrop for examining how Seattle Mayor Katie Wilson’s communications team handles difficult news. In this edition of “The Spin,” KIRO Newsradio reporter Luke Duecy looks at two recent examples and the […]

2 days ago

Steel shortage derailing plans to complete ‘Revive I-5′ project