A steel shortage is derailing plans to complete the massive “Revive I-5” project in Seattle.

The Washington State Department of Transportation said pavement repairs from southbound I-5 between I-90 and Spokane Street are on schedule, but a lack of steel could push back the completion date of another part of the two-year project.

A major component of the $25.6 billion project is installing more than 50 expansion joints.

“Expansion joints allow the freeway to expand and contract with heat, cold, and heavy-duty traffic,” said Tom Pearce of WSDOT.

So far, crews have yet to replace even one.

“Our contractor is having a little bit of an issue procuring steel for this,” Pearce said. “It’s probably going to be late August, early September before they can get the steel that they need.”

So, how does that impact your drive on I-5?

According to WSDOT, there will not be weekend morning lane reductions for at least a few weeks. So far, only two of 16 planned weekend closures have happened.

Revive I-5 returns to Seattle with a full freeway closure

“This year, we’re hoping to get as many weekends in as possible,” Pearce said.

Pearce says as soon as the contractor gets the needed steel, crews will begin installing a few expansion joints at a time.

“It’s a big undertaking to replace these expansion joints because we have to reduce the freeway down to one or two lanes,” Pearce said.

In the meantime, pavement repairs will continue.

MyNorthwest News

oak harbor...

Lexi Herda, KIRO 7 News

Oak Harbor High School student trapped under car after being hit in marked crosswalk

An Oak Harbor High School student was rushed to the hospital after they were hit by a car and became trapped underneath the vehicle.

10 hours ago

3 - Tacoma Narrows Bridge...

KIRO 7 News Staff

Expect long PM commutes until further notice on the Tacoma Narrows Bridge

Drivers who use the Tacoma Narrows Bridge (SR 16) to Gig Harbor should expect longer nighttime commutes due to construction work.

11 hours ago

online portal...

James Lynch

King County launches online portal to give crime victims easier access to case updates

Many crime victims in King County will be able to check key information about their cases online through a new secure portal announced by King County Prosecuting Attorney Leesa Manion.

12 hours ago

Garth Brooks adds 4th show to Seattle stop during "Blame It All On My Roots" tour...

Regan Gallo-Fenz

Garth Brooks adds 4th show in Seattle

Country-music artist, Garth Brooks, adds a fourth show to his Seattle itinerary at Climate Pledge Arena in November.

12 hours ago

football player killed...

KIRO Newsradio staff

Driver held on $200,000 bail after car strikes, kills Federal Way football player

A Federal Way High School football player died in a crash Friday night.

13 hours ago

test drive...

Julie Berg, KIRO 7 News

82-year-old man assaulted and car stolen during Whatcom County test drive

An 82-year-old man was violently assaulted and had his vehicle stolen during a test drive Thursday, on Aldrich Road in Whatcom County.

13 hours ago

Steel shortage derailing plans to complete ‘Revive I-5′ project