‘30 truckloads from the finish line’: West Seattle Bridge reopening jeopardized by concrete strike

Feb 14, 2022, 5:10 AM | Updated: 9:20 am

West Seattle Bridge...

A vantage point on the West Seattle Bridge from Beacon Hill. (Flickr)

(Flickr)

The West Seattle Bridge has been closed since March 2020, and while the bridge was originally timed for reopening in June 2022, city leaders are concerned that the materials needed for repair are being throttled by Teamsters 174’s strike with the region’s concrete suppliers.

In a news conference last week, Seattle Mayor Bruce Harrell and King County Executive Dow Constantine marked Feb. 20, 2022, as the “drop dead” date for delivery resumption of SDOT’s concrete supply before West Seattle Bridge repairs are delayed.

Pressure mounts in concrete strike as King County offers $35 million bargaining chip

Mayor Harrell pointed out that specialized concrete blocks are required to hold the bridge’s steel cables for support and strength, and the relevant materials requests are due by Feb. 20 to maintain a repair schedule at the current 60 hours a week schedule.

“We are just 245 yards – fewer than 30 truckloads – from the finish line. I call on concrete suppliers to reach agreement with Teamsters Local 174 as soon as possible to ensure completion of the West Seattle Bridge repair is as scheduled,” Councilmember Lisa Herbold wrote in a news release.

Herbold noted that the West Seattle Bridge repair is an “emergency project” that, while in progress, cuts off businesses and workers on the West Seattle peninsula from the rest of the city. She adds that the bridge has been in use for 40 years, and the rest of the region’s transportation system is built around it.

As of Feb. 13, negotiations between Teamsters 174 and the six concrete suppliers remain at an impasse. Late last week, the union, which represents 300 striking workers, appeared on the steps of one the suppliers, Gary Merlino Construction, to demand talks continue after negotiations failed with a federal mediator in late January.

In a joint news release on behalf of Glacier, Stoneway, Salmon Bay, and Cadman, the suppliers named the event “an orchestrated media obstacle” and called on Teamsters 174’s secretary-treasurer to speak with “the Western Regional Director FMCS and [work] through her to arrange for a meeting as the Companies desired and communicated at the end of the mediation session of January 20.”

“We believe a controlled and professional negotiation with a federal mediator is the best way for the parties to arrive at a settlement,” the release stated.

In December, SDOT reported that it was in the final stages of the West Seattle Bridge’s repair, telling KIRO Newsradio that more than 91 tons of additional steel cable, carbon fiber, and the filling of concrete cracks with epoxy are among the final fixes to be made.

“Repair of the West Seattle bridge remains one of the City of Seattle’s highest priorities,” Mayor Harrell noted in a Feb. 9 news conference. “While the Seattle Department of Transportation, contractors, and community partners have worked tirelessly to keep the West Seattle Bridge reopening on track for mid-2022, this continued strike threatens to delay that schedule.”

“For an on-time opening, concrete companies and workers must return to mediation and reach a fair agreement – further delay and uncertainty is untenable for hundreds of thousands of neighbors across West Seattle, our city, and the entire region.”

KIRO Newsradio’s Chris Sullivan contributed to this report. 

MyNorthwest News

amazon pregnant lawsuit...

MyNorthwest Staff

Amazon hit with class action lawsuit alleging widespread discrimination against pregnant employees

Amazon was hit with a proposed nationwide class action lawsuit, alleging the company systematically discriminated against thousands of its pregnant employees.

29 minutes ago

gig harbor monoxide leak...

KIRO 7 News Staff

Gig Harbor man and woman in critical condition after carbon monoxide leak in their home

A man and woman are in critical condition following a carbon monoxide leak at their Gig Harbor home. The pair and their dog were found inside their home.

2 hours ago

spokane school suspect killed...

Jason Sutich

Armed suspect killed by deputy outside Evergreen Middle School in Spokane

Evergreen Middle School in Spokane went into lockdown after a deputy shot and killed a suspect, allegedly armed with a Glock 19, who approached the school.

3 hours ago

Seattle seahawks home opener...

JAKE CHAPMAN, KIRO 7

12s, Seattle businesses get ready for Seahawks home opener

Thousands of people are expected to flood Pioneer Square and the SoDo neighborhood as the Seattle Seahawks prepare for their home opener against the Patriots.

4 hours ago

mattawa irrigation canal dies grant county...

Jason Sutich

Moses Lake woman arrested for allegedly pulling knife on public servant, stealing cat

A 21-year-old Moses Lake woman was arrested Monday for allegedly pulling a knife on a public servant and stealing his cat.

4 hours ago

seattle dealers recovery housing...

Charlie Harger

Harger: Two blue cities decided dealers don’t belong in recovery housing. Seattle hasn’t

I've heard from people who've lived in permanent supportive housing in Seattle. Drugs move through the building around the clock, and staff look the other way.

5 hours ago

‘30 truckloads from the finish line’: West Seattle Bridge reopening jeopardized by concrete strike