WSDOT runs into even more problems on the 520 bridge project

Sep 12, 2013, 6:15 AM | Updated: 4:01 pm

The 520 bridge replacement project is more than a year behind schedule and now the Washington State Department of Transportation says there is another problem with one of the pontoons that will float the bridge over Lake Washington.

The state has just finished repairing the second pontoon at a Seattle dry-dock to repair and seal cracks caused by a design flaw that wasn’t caught until after they were constructed.

The state was so proud, it just released a video with deputy construction manager Greg Meadows.

But instead of floating out into Lake Washington, Pontoon W left that dry-dock and went straight to another repair facility along the Duwamish River. That’s because six of the 10 columns built on top of the pontoon need to be demolished and rebuilt. The contractor says the reinforcing rebar inside those columns shifted during construction.

That contractor, Kiewit Construction, will have to eat the costs to replace those columns, and it doesn’t expect the extra one or two months it will take to do that will add a lot of time to the already overdue project.

As for the costs of this project, the overruns are mounting.

Some estimates put them at close to $400 million right now. Keith Metcalf is the interim chief engineer on the project. “When you look at all the potential risks that have been identified by the contractor, a lot of those haven’t even been agreed that they’re real yet,” he said.

A $250 million contingency fund was built into this $4 billion project, but that appears to be way short of what will be necessary.

And that’s on the taxpayers. It works out that way because the state, not the contractor, designed the pontoons. “Because there was a design error that we acknowledged and owned up to, we own, the taxpayers own the changes that result,” said Metcalf.

Former transportation secretary Paula Hammond said earlier this year that doing the design work in-house was supposed to save the taxpayers money. “We were $189 million ahead on this pontoon project as we came out of the gate,” she said. “Had that pontoon design (been) perfect, we would have come out of that smelling like a rose.”

Instead, the project is likely going to end up hundreds of millions of dollars in the red.

The new bridge was supposed to open sometime next year. It now looks like it won’t open until the end of 2015 or the spring of 2016.

MyNorthwest News

town hall seattle wedding...

KIRO Newsradio staff

Judge dismisses double-murder case against man accused of Seattle ax attacks

A King County judge dismissed the double-murder case against Liam Kryger Thursday.

3 hours ago

search for 19-year-old lake washington...

MyNorthwest Staff

Body of 19-year-old who went missing on Lake Washington recovered

The body of a 19-year-old man who went missing on Lake Washington was recovered Thursday.

3 hours ago

20 cats AirTag stolen vehicle Tacoma Truck...

Frank Lenzi

Deputies find 20 cats in stolen truck after AirTag tracks down vehicle in Tacoma

An AirTag led Pierce County Sheriff's Deputies to a stolen truck — and 20 cats — in Tacoma this week.

4 hours ago

Woodland park zoo sloth...

KIRO 7 News Staff

Woodland Park Zoo welcomes second sloth, hopes pair will ‘hang out’ soon

A 26-year-old female Hoffmann’s two-toed sloth named Jessie has arrived at Woodland Park Zoo as part of a national breeding program.

5 hours ago

tsunami...

Frank Lenzi

Alaska earthquake could send 20-foot tsunami waves to Washington coast in just 3.5 hours, new study warns

A new study from the Washington Geological Survey finds tsunami activity could last 24 hours or more, and the first wave might not be the biggest.

6 hours ago

kiro newsradio national edward r. murrow award...

Frank Lenzi

KIRO Newsradio wins 2026 National Edward R. Murrow Award for Breaking News Coverage

KIRO Newsradio 97.3 FM has won a 2026 National Edward R. Murrow Award for breaking news coverage of its reporting on the Seattle ICE protests that turned violent.

7 hours ago

WSDOT runs into even more problems on the 520 bridge project