Oct 25, 2017, 7:59 AM | Updated: 3:05 pm

transportation levy...

(KIRO 7)

(KIRO 7)

At $930 million, the 2015 Move Seattle levy is the biggest in city history.

RELATED: How Washington could turn freeways over to self-driving cars

A property tax increase over nine years is funding transportation projects large and small across the city.

But the most recently available progress report suggests the city is at risk of not making many of its levy targets for 2017, and some levy money is being deferred for future use.

The Seattle Department of Transportation left $32 million in levy money unspent in 2016 and carried it forward into 2017.

The city expects a similar carryover into 2018.

“What we’re seeing the first couple of years are a lot of smaller projects coming forward, more curb ramps, a lot of refreshed striping, our new tree trimming crew is on board and out trimming trees and next year we’re going to start seeing some of those bigger projects start getting delivered,” SDOT director Scott Kubly said.

Kubly says the city is still ramping up the nine-year levy, hiring staff and designing big projects.

He says spending will jump in later years when more construction begins.

“I would actually argue that the fact that we have carryover is an indication of us being responsible,” Kubly said.

Kubly says designing projects before voters approved funding would not have made sense.

SDOT’s latest levy report, for the second quarter of this year, shows the city far from its 2017 commitments.

For example, it committed to re-mark 1,500 crosswalks in 2017 but finished only 527 in the first half of the year.

Of the 560 lane miles committed for restriping, only 25 were done by the end of June.

SDOT said only about a third of the spending is done in the first half of the year because some work, like paving, has to wait until the weather improves.

The third-quarter progress report for Move Seattle will be released in November to an oversight committee.

Shefali Ranganathan of the Transportation Choices Coalition, who serves as co-chair of the oversight committee, said SDOT’s pace of spending has been discussed at the meetings, but “I’m not concerned at this point.”

Kubly said it is more important to judge the success of the levy in a few years, once design work is farther along and more workers are hired.

The Move Seattle levy includes major projects like an overpass at Lander Street and a rebuilding of a bridge along Fairview Avenue.

MyNorthwest News

killer whale calf...

KIRO 7 News Staff

A new southern resident killer whale calf was born to J35

The Center for Whale Research announced that a new calf has been born in the southern resident killer whale population.

19 minutes ago

train puyallup...

MyNorthwest Staff

Man in wheelchair killed after being hit by train in downtown Puyallup

Two people have been hit by a train in downtown Puyallup.

47 minutes ago

card skimming...

James Lynch

Card skimming losses top $1 billion as Secret Service targets local fraud

The U.S. Secret Service is working in the Seattle area to find and remove illegal card-skimming devices at retailers, ATMs, and gas pumps.

55 minutes ago

amazon (2)...

Julia Dallas

Amazon responds to lawsuit alleging it failed to protect employee who reported rape by senior manager

An Amazon employee is suing the company, alleging it failed to protect her after she reported that a senior manager raped her.

1 hour ago

homelessness (1)...

Luke Duecy

Seattle’s new homelessness plan aims to move people into housing. Here are the big questions

Seattle Mayor Katie Wilson is betting that a more coordinated approach to homelessness can get more people off the streets, but questions remain.

2 hours ago

Snoqualmie Pass Closure...

MyNorthwest Staff

Westbound I-90 back open at Snoqualmie Pass after winter preparation

Westbound I-90 has reopened after a temporary closure at Snoqualmie Pass.

4 hours ago

Kubly: Seattle late on projects because it’s ‘being responsible’