Gov. Inslee astounded by Seattle tunnel contractor’s decisions to stop quality control

Jan 20, 2016, 8:50 AM | Updated: 12:56 pm

“We do already know that the contractor – for reasons that are just astounding to us &#...

"We do already know that the contractor - for reasons that are just astounding to us - stopped doing quality control work that they had been doing for the first thousand feet," Gov. Jay Inslee told Seattle's Morning News. (WSDOT)

(WSDOT)

The contractor responsible for operating the Seattle boring machine stopped doing quality control work sometime before a sinkhole opened up at the city’s waterfront.

Gov. Jay Inslee told Seattle’s Morning News that after the sinkhole opened behind Bertha Jan. 19, it became apparent that Seattle Tunnel Partners was not doing what it needed to in order to guarantee safety.

“We do already know that the contractor &#8211 for reasons that are just astounding to us &#8211 stopped doing quality control work that they had been doing for the first thousand feet,” Inslee said.

Related: Seattle considers cottage industry to ease housing, rent concerns

It was a comment that KIRO Radio’s Dave Ross wanted to make sure he heard correctly. The contractor stopped doing quality control work?

For the first 1,000 feet of work, crews with Seattle Tunnel Partners measured the amount of dirt being removed from the tunnel, Inslee explained. That helped prevent sinkholes, by making sure there wasn’t a “void.” But for reasons Inlsee couldn’t explain, they stopped doing that work.

“We are very disappointed that the contractor failed in that regard,” Inslee added.

Inslee ordered the work involving Bertha stopped. The contractor now has to complete a root-cause analysis of how and why the sinkhole appeared and how crews will prevent it from happening again. Inslee hopes this will be done as “soon as humanly possible,” because the project is already two years behind schedule.

“This thing is going underneath the viaduct, and we know how fragile that is,” Inslee said. “Everyone knows a sinkhole under the viaduct could be catastrophic and we cannot have that risk without being assured that they’re going to preform quality control necessary to prevent that from happening again.”

Why not just stop Bertha, before it does some real damage?

It comes down to the money already invested in the project, Inslee explained.

“To throw money overboard and waste it does not seem [reasonable],” he said.

Inslee said the project still has a “reasonable chance of success.”

MyNorthwest News

bus crash light rail...

Jake Renn, KIRO 7 News

Link light rail train involved in crash with bus, trains delayed

Link light rail trains have been delayed this morning, Sept. 15, because of a crash with an empty school bus.

37 minutes ago

closures...

Nate Connors

Expect delays: WSDOT has a busy week of closures planned across the region

Most of this week's lane and ramp closures are a continuation of the region's pavement repair projects scheduled to wrap up in the spring of 2027.

45 minutes ago

wa coast earthquake...

KIRO 7 News Staff

Magnitude 3.8 earthquake hits off the coast of WA, British Columbia

A magnitude 3.8 earthquake hit off the coast of British Columbia and Washington State early this morning.

2 hours ago

This image depicts a dark circuit board surface with a glowing blue AI chip hovering above. (Image:...

Jake Skorheim

Jake: The suddenness of AI doomerism is suspicious

AI is now, apparently, an existential threat to humanity, and that only aggressive government regulation stands between us and extinction.

2 hours ago

Peter and Michelle...

James Lynch

Former KOMO 4 photographer Peter Mongillo remembered as a master storyteller

Former KOMO 4 photographer Peter Mongillo has died after a battle with esophageal cancer.

2 hours ago

Fall City...

MyNorthwest Staff

Fall City teen accused of killing family back in court for hearing to determine if he’ll be tried as an adult

The Fall City teen accused of killing his family is back in King County Court for a hearing that'll determine if he's tried as a juvenile or an adult.

3 hours ago

Gov. Inslee astounded by Seattle tunnel contractor’s decisions to stop quality control