Washington Secretary of Transportation not willing to call ‘fail’ on Bertha yet

Feb 11, 2014, 1:37 PM | Updated: Feb 12, 2014, 7:38 am

Washington Secretary of Transportation Lynn Peterson tells Dori Monson they’re not at a point...

Washington Secretary of Transportation Lynn Peterson tells Dori Monson they're not at a point where they'd be making a decision to abandon the tunnel project. (WSDOT Image)

(WSDOT Image)

After two months of delays and word it will likely be several months more before tunnel-boring machine Bertha will get moving again, some were calling for officials to cut our losses and move on to another viaduct replacement alternative.

“It’s time to pull the plug on this project. It’s time for a public official to be responsible of our tax dollars and say this is ending up costing us too much,” said KIRO Radio’s Dori Monson.

In an appearance on The Dori Monson Show Tuesday, Washington Secretary of Transportation Lynn Peterson acknowledged while their main role is to oversee the stewardship of taxpayer dollars, they’re not at a point where they’d consider abandoning the project.

“I don’t think we’re at that decision point yet,” said Peterson. “It’s obviously at the top of our list to make sure the contractor and the manufacturer get the fix done, get it done as quickly as possible in a safe environment. We will be pushing for that.

“If we get to that point where they come back and they have different information than what they had anticipated, we will have to have a conversation with the community.”

Peterson painted that as a “worst case scenario.” She said this week the tunnel contractor will be meeting with the boring machine manufacturer to determine the best ways to make repairs to the broken seals surrounding the main bearing of the boring machine.

“We will be getting an update on Friday of exactly how they plan to work on the pieces of the machine that need to be replaced and maintained,” said Peterson.

There are a few options on how they’ll approach the fix. She said they may go in from a hole above the machine or they may move in through the tunnel on the backside of the machine.

While the machine is currently in a good position to do repairs from the top – there’s nothing above her, said Peterson – Monson asked what happens when Bertha finally makes her way further under the city.

“What happens if it goes another couple thousand feet and it’s directly underneath buildings or skyscrapers and now you don’t have that topside access, then what?”

“I think that before we even get to that scenario, we would be playing our strong oversight role and making sure that we believe everything has been done to insure that the machine doesn’t stop underneath the city of Seattle,” said Peterson.

“But presumably, you guys did that before you started as well, and it only went 1,000 feet,” said Monson.

“There’s a lot of questions that need to be worked out between the contractor and Hitachi [boring machine manufacturer] on what exactly caused those five seals to fail between operation of the machine and the design of the machine itself, so getting that worked out right now is extremely important,” said Peterson.

As to who will cover the costs, Peterson said: “All of the evidence that we have to date is pointing to the fact that this is on the contractor and the manufacturer.”

All the workers involved in the excavation are still busy, even though Bertha isn’t digging, Peterson said.

“There’s a lot of work going on within the tunnel and at each end there are hundreds of folks that are employed by this project and they all have work to do in the meantime,” said Peterson.

“That’s hard for me to imagine,” said Monson. “Is it busy work or is it necessary work?”

“It’s all very necessary work. In fact, the work that’s going to be conducted just to make sure that they can get to her and start working on her, will be part of what they do.”

In the meantime, Peterson asked for the public’s patience. “I am as frustrated as any other citizen of Washington that wants to see this thing moving and completed.”

She said they’re doing their best to make sure the decision that was made by a vote of the public gets carried out in the most diligent way possible.

“We just need to be very aware that every tunneling project has its difficulties and we’re experiencing one right now. We’re actually experiencing it in the best spot it could have happened and that we are doing everything we can to get it fixed and moving as quickly as possible,” said Peterson.

Related:
State to hold contractor accountable on tunnel
Dori Monson: Bury Bertha, build a bridge
Bertha not expected to move for months

MyNorthwest News

_spokane wildfires...

Luke Duecy

Convicted felon arrested in connection with Old Trails Fire in Spokane

Governor Bob Ferguson said federal resources are on the way to help Washington battle 17 major wildfires burning more than 260,000 acres.

6 hours ago

pierce transit (1)...

Nate Connors

Chill out during this week’s heat wave courtesy of Pierce Transit

It's become a regular service to Pierce County residents during the excessive heat bursts we often get throughout our summer season.

8 hours ago

Gifford Pinchot National Forest (1)...

Julia Dallas

Gifford Pinchot National Forest issues emergency closures for wildfire

The Gifford Pinchot National Forest has issued an emergency closure order for the High Lava Fire.

9 hours ago

washington...

James Lynch

Crime drops across every major category in Washington, but officials warn the full picture is more complicated

Crime declined across every major category in Washington in 2025, with sharp drops in murders, violent crime, and property crime.

9 hours ago

seattle homelessness...

Frank Lenzi

Seattle, King County plan to reclaim nearly $160M in homelessness contracts from KCRHA

The King County Regional Homelessness Authority (KCRHA) will survive despite calls from some Seattle and King County leaders to dissolve it.

10 hours ago

King County Metro...

KIRO 7 News Staff

King County Metro to add 9 new bus routes and 3,000 additional weekly bus trips to schedule

King County Metro is adding nine new bus routes and more than 3,000 additional weekly bus trips to its schedule.

10 hours ago

Washington Secretary of Transportation not willing to call ‘fail’ on Bertha yet