CHOKEPOINTS

Fish culvert work to shut down road to Granite Falls for 13 days

Jul 3, 2018, 4:58 AM

culverts, fish passage improvements...

The Washington State Department of Transportation continues to replace hundreds of culverts. (WSDOT)

(WSDOT)

Granite Falls drivers have had their appetizer. Now it’s time for the main course, a 13-day closure of their primary route in and out of town.

RELATED: What are those mysterious white blocks in Tacoma?

Highway 92 drivers have survived two weekend closures at Machias Road as the state replaces the fish culvert on Little Pilchuck Creek. This time, it’s 13 straight days of closures starting Friday.

“It is a complete closure of that intersection,” Frances Fedoriska with the Washington State Department of Transportation said. “The detour routes that were in place for these last two weekends are the same detours that everyone has to take during the 13-day closure.”

Cars can use the quick detour, which uses the nearest streets. It adds about a mile. Truck drivers are being asked to use the longer detour route, which takes them to Highway 9 and 84th Street Northeast.

During the weekend closures, workers injected jet grout into the ground to stabilize the area and prep for rerouting the Little Pilchuck Creek.

“We’ve been able to stabilize the hillside that’s going to hold up this massive 60-foot buried bridge, which is quite a bit heavier than the tiny, little 12-by-6 foot culvert that was there previously,” Fedoriska said.

This is not just some cut-and-cover project. Crews are taking out the road, digging out the dirt down to stream level, and then putting a bridge over the top.

“There are more than 20 pieces of this bridge,” Fedoriska said. “They’re going to be delivered to the site, and we’re going to assemble it in the creek bed, pave on top of it, and re-open the road.”

The project is all part of the federal court mandate that requires the state to restore natural fish habitat that is blocked by roads or bridges.

“The fish will have an easier time passing through it and it will open up 30 miles of habitat that was incredibly difficult for migrating species to get to,” Fedoriska said.

If everything goes according to plan, State Route 92 will re-open July 19. There will be some smaller closures about a month later as the contractor re-stripes the road and adds landscaping.

Chokepoints

kingston ferry...

Chris Sullivan

Kingston’s new ferry ticket kiosk cut the line-cutting. Now it needs to fix the GPS problem

The Washington State Ferries put in a new ticket kiosk approaching the Kingston dock earlier this year to help ease congestion and line cutting.

11 hours ago

garbage truck fire NB I-5...

Jason Sutich

NB I-5 off-ramp to West Seattle back open after garbage truck fire

The exit ramp to West Seattle from northbound I-5 is fully blocked on Monday while a garbage truck burns in the middle of the roadway.

24 hours ago

tacoma car crash fatal...

MyNorthwest Staff

One killed after car splits in half in violent Tacoma crash

The collision happened just after 11 p.m. on Portland Avenue. A 28-year-old man, Duran Tessema, hit a power pole so hard that it cut his car in half.

1 day ago

9th ave...

Chris Sullivan

SDOT plans to paint over Convention Center street art that won’t come off 9th Ave.

SDOT, which granted the Seattle Convention Center the permit to paint 9th Ave., now has a plan to fix the problem.

4 days ago

I-405 (2)...

Nate Connors

A full closure of I-405 will make for a rough weekend commute

The Washington State Department of Transportation (WSDOT) has scheduled a full closure of northbound I-405 between Renton and Bellevue.

4 days ago

road with paint seattle convention center...

Chris Sullivan

Seattle Convention Center paints itself into a transportation mess on 9th Ave

A Seattle Convention Center art event left a key I-5 access road covered in paint that can't be removed, and there's no timeline to reopen.

5 days ago

Fish culvert work to shut down road to Granite Falls for 13 days