girder, Tacoma...

In February 2020, construction crews are beginning the process of installing bridge girders on the new southbound I-5 Puyallup River Bridge. This photo gives you an idea of the size of these girders. (Washington State DOT/Flickr)

(Washington State DOT/Flickr)

Time for our first Chokepoints of the year, and 2021 is starting with a bang. The state is about to move what is believed to be the biggest girder ever made in the United States into place over the Puyallup River in Tacoma.

This girder is 223 feet long, 9 feet high, and over 250,000 pounds. Contractors must place it over the Puyallup River and the rail yard below to help complete the new southbound I-5 bridge.

“The reason why it is as long as it is because it has to span all of the rail lines that are down in that vicinity,” said Cara Mitchell from the Washington State Department of Transportation. “It’s kind of on an angle, too.”

For some perspective, this girder is longer than the wingspan of a 747.

“From what we can tell, it’s the largest pre-stressed concrete girder made in North America, and it’s being made right here in Tacoma,” Mitchell said.

But this massive girder is just one of 30 girders left to place to complete the backbone of the southbound I-5 Puyallup River Bridge.

“They are anywhere from 170 feet to 220 feet, and then we have the 223 foot one,” Mitchell said. “It’s a variety of lengths, and there’s three different spans that we have to cover.”

The contractor started moving these girders into place Monday. Between three and five of them will be put into place each night until the lifting is done.

“They are scheduling three weeks of work, but if they can get it done sooner, that’s great,” Mitchell said.

Drivers should expect an overnight lane closure on southbound I-5 across the Puyallup River every Monday through Thursday until the work is completed. There will also be ramp closures at Portland Avenue, Bay Street, and Port of Tacoma Road. The final week will see two lanes of southbound I-5 blocked.

“We are also coordinating this work with the rail lines,” Mitchell said. “If we find out there’s a train coming through, we have to stand down. It’s a coordination effort that’s happening every single night.”

High winds could also delay the work.

This is the last huge piece of the Tacoma expansion puzzle before work is expected to wrap up in the fall, but Mitchell says the to-do list is still pretty lengthy.

“We have the L Street overpass that we still have to finish up, and we have the mainline road surface that has to be finished,” Mitchell said. “Setting all that barrier up, and getting the striping in for HOV, and all the signage. There’s a lot of work that’s ahead of us, but 2021 is going to be busy, busy getting this project buttoned up.”

The hope is to have everything open to traffic during the fall.

We always joke that the freeways in Tacoma have been under construction for decades, and they really have been. There have only been a few years over the last quarter century where there wasn’t construction blocking lanes or adding hassle to the drive.

This technically started last century when the state started rebuilding the I-5/Highway 16 interchange through South 38th Street.

And just as this project wraps up, the state is ramping up the Gateway Project, which extends Highway 167 from Puyallup to I-5 in Tacoma, and State Route 509 to the Port of Tacoma. So look for more construction disruptions there.

And of course, the widening continues just to the south through JBLM to DuPont.

The Tacoma area has a few more years of this left to go.

Check out more of Chris’ Chokepoints.

Chokepoints

I-405 expansion...

Chris Sullivan

Sullivan: I-405 expansion to widen freeway in Bothell is underway

We've all seen I-405 expanding between Bellevue and Redmond, but construction to widen the freeway north of Bothell is now underway as well.

2 days ago

revive i-5 seattle...

Nate Connors

I-5 repair work to slow spring breakers, baseball fans this weekend

Beginning Friday night, three lanes of I-5 north between Albro Place and the West Seattle Bridge through Monday morning at 5 a.m.

4 days ago

Photo: April is Distracted Driving Awareness Month. Washington drivers can face higher insurance ra...

Nate Connors

Has your insurance gone up? Rates can take a hike for distracted drivers

April is Distracted Drivers Awareness Month. The President of NW Insurance Council says it has been working on prevention for years.

6 days ago

Signs in the eight light rail stations will provide real-time travel data for trains and destinatio...

Chris Sullivan

It’s not the whole enchilada, but light rail to roll on Eastside this month

Light rail service on the Eastside begins later this month. The eight stations are ready to roll. Test trains are running on the tracks.

7 days ago

Image: All general-purpose lanes were blocked leaving just the left HOV lane open on I-5 south of 2...

Steve Coogan

Military vehicle accident on I-5 north in Federal Way cleared after snarling traffic

A rollover vehicle accident Wednesday caused significant backups and delays for multiple hours before being cleared.

7 days ago

Rapid-Ride G Line...

Micki Gamez

RapidRide G Line: A new bus route connecting riders to mass transit

King County Metro's (KCM) Al Sanders said the RapidRide G Line will kick off shortly after the Lynwood extension is done in early September.

7 days ago

Tacoma freeways near end of 20-plus year construction cycle (kind of)