CHOKEPOINTS

Why Bellevue didn’t pick a Bertha to dig its light rail tunnels

Mar 2, 2017, 6:05 AM | Updated: Mar 16, 2017, 9:52 am

Bertha, Bellevue...

Bertha before the boring machine mined under Seattle. (WSDOT)

(WSDOT)

Sound Transit contractors are tunneling under downtown Bellevue, but you won’t find a big tunnel-boring machine like Seattle’s Bertha.

The light rail tunnel will connect the East Main light rail station at 112th Avenue SE and Main Street to the Downtown Bellevue light rail station at NE 6th Street, near the existing Bellevue Transit Center.

Sound Transit is using the Sequential Excavation Method (SEM), a way of digging shorter light rail tunnels. On the Eastside, they are looking at a shallow, half-mile-long tunnel — not like the Northgate Tunnel which will be 3.5 miles long.

SEM minimizes the disruption to surface streets and buildings while reducing noise around the construction site. The other big reason SEM was picked for the Eastside?

“SEM doesn’t require the same amount of muck-hauling (taking away dirt that has been excavated) that TBM (tunnel boring machine) mining does because far less dirt is being mined,” said Kimberly Reason with Sound Transit.

Bellevue vs. Seattle tunneling

People in the Northgate and Roosevelt neighborhoods know all about that, Reason points out.

“The Northgate Link tunnels, when open in 2021, will serve two underground stations 85-90 feet underground,” she said. “So we needed to use (tunnel boring machines) for those.”

Sound Transit used SEM to dig the Beacon Hill light rail station several years ago and now some of those same experts are working on the Bellevue tunnel, which is set to open in 2023.

According to Sound Transit, the Sequential Excavation Method works like this:
• First, excavators begin digging out a small section of the tunnel. That soil is removed.
• Reinforcing lattice girders are installed.
• Pressurized concrete, called shotcrete, is sprayed onto the tunnel sides, ceiling and floor.
• This process is repeated. Finally, the entire tunnel is covered with waterproofing and an additional layer of one-foot thick concrete.

Chokepoints

9th ave...

Chris Sullivan

SDOT plans to paint over Convention Center street art that won’t come off 9th Ave.

SDOT, which granted the Seattle Convention Center the permit to paint 9th Ave., now has a plan to fix the problem.

2 days ago

I-405 (2)...

Nate Connors

A full closure of I-405 will make for a rough weekend commute

The Washington State Department of Transportation (WSDOT) has scheduled a full closure of northbound I-405 between Renton and Bellevue.

2 days ago

road with paint seattle convention center...

Chris Sullivan

Seattle Convention Center paints itself into a transportation mess on 9th Ave

A Seattle Convention Center art event left a key I-5 access road covered in paint that can't be removed, and there's no timeline to reopen.

3 days ago

sb i-5 semi-truck backup...

Jason Sutich

All lanes of SB I-5 reopen near Ship Canal Bridge after semi-truck collision caused 7-mile backup

All lanes have been reopened along southbound I-5 near the Ship Canal Bridge after a collision involving a semi-truck.

4 days ago

bus crash light rail...

Jake Renn, KIRO 7 News

Link light rail train involved in crash with bus, trains delayed

Link light rail trains have been delayed this morning, Sept. 15, because of a crash with an empty school bus.

5 days ago

closures...

Nate Connors

Expect delays: WSDOT has a busy week of closures planned across the region

Most of this week's lane and ramp closures are a continuation of the region's pavement repair projects scheduled to wrap up in the spring of 2027.

5 days ago

Why Bellevue didn’t pick a Bertha to dig its light rail tunnels