Lost in all the Alaskan Way Viaduct and tunnel talk is what is going to happen to the Battery Street Tunnel.

RELATED: How Seattle plans to demolish the Alaskan Way Viaduct
RELATED: Bus riders need to prepare for viaduct closure, too

There have been some last-minute attempts, that we have talked about before, to save the Battery Street Tunnel. Some believe it would be a waste to simply fill it in.

Advocates have proposed turning it into a park, or a bike and pedestrian through-way. None of that is going to happen. The 64-year-old Battery Street Tunnel will be filled in. A lot of that fill material will be coming from the broken-down concrete of the demolished Alaskan Way Viaduct.

Phil Wallace of demolition contractor Kiewit said they have to remove all the metal rebar first, and then the concrete will head into the Battery Street Tunnel.

“We’re going to take it down to Terminal 25, crush it down to three-inch-minus and put it in the tunnel,” Wallace said.

Three-inch-minus, for those that aren’t in the construction business, means the pieces of concrete will be crushed into chunks that are three-inches across, or less. Wallace said all of that debris will fill the base of the 2,000-foot-long tunnel.

“We’ll bring it up to a 10 foot, plus or minus, level within the tunnel, and then the tunnel from that to the top is filled with what they call a cellular concrete,” he said.

Cellular concrete is a type of concrete and foam mix that is easier to dig-into. It should be good for future needs, should the city want to put utilities through the area.

We don’t have the final timeline for filling-in the Battery Street Tunnel or when it will be finished, and Wallace said they have work to do first.

“There’s a lot of work we need to do in the tunnel before we can place material in there,” he said. “There are a lot of utilities we have to re-route.”

The Battery Street Tunnel will remain open through the three week closure of Highway 99.  You will still be able to get on or off at Western Avenue.

Chokepoints

ritzville i-90 closed visibility...

Jason Sutich

I-90 in Ritzville reopens after dust storm caused multiple collisions

I-90 in Ritzville has reopened after both directions were blocked Friday due to multiple collisions.

2 days ago

super load marysville...

Chris Sullivan

Super load stuck on I-5 south in Marysville should move tonight

A truck carrying a massive pre-fab building has been parked along the southbound I-5 ramp at 88th St. in Marysville for three days.

3 days ago

closure (1)...

MyNorthwest Staff

I-5 reopens in both directions between Maytown and Tumwater

I-5 has reopened in both directions in Thurston County at milepost 97, KIRO Newsradio confirmed.

3 days ago

oyster run anacortes...

Nate Connors

43rd annual Oyster Run returns this weekend in Anacortes

The Oyster Run welcomes thousands of motorcyclists to Skagit County by Figaldo Bay. It's loud, it's proud, and it takes over Anacortes this time each year.

3 days ago

sounder train shoreline...

MyNorthwest Staff

All S Line trains stopped after woman hit in SODO

All Sound Transit S Line trains have been stopped after a woman was hit in SODO Thursday.

3 days ago

Pinehurst Station light rail...

Chris Sullivan

Sound Transit to open new light rail station 5 years ahead of schedule

Sound Transit isn't known for being on time or on budget with its light rail projects, but it's about to open a new station way ahead of schedule.

4 days ago

How crews will fill in Seattle’s Battery Street Tunnel