WSDOT working hard to clear landslide blocking portion of I-5

Dec 28, 2015, 11:34 PM | Updated: May 7, 2016, 11:35 pm

You should expect delays getting back to Seattle if you’re traveling on I-5 New Year’s Eve.

One lane of northbound I-5 remains closed just north of Portland. Plans are in place to get it re-opened in about a month.

The right lane of I-5 just outside Woodland has been closed since heavy rains brought down the hillside Dec. 9. Boulders the size of SUV’s came down, along with mud, trees and other debris.

Tell us what slows you down each day

Over the last few weeks workers have brought down any remaining unstable materials and prepped the hillside for a permanent fix.

“We have geotechnical engineers who are continuing to monitor the hillside to make sure any movement is recorded and we can take that into consideration for long-term plans for stabilizing the hillside and reopening that third lane of I-5,” Washington State Department of Transportation spokesperson Tamara Greenwell explained.

Greenwell says the department is hiring workers and finding specialized equipment to begin stabilizing the hillside next week.

“What we’re working to do and working to get is equipment that will insert and grout about 50-foot long steel rods into the hillside and that will act as a stabilizer to keep the hillside from coming down again,” she said.

That work should take about a month. Greenwell says they hope to have all lanes of I-5 northbound re-opened by the end of January.

But if drivers are heading south for the holiday weekend, they will need to add extra time for the return trip to get through the closure.

Greenwell says the backups over the Christmas holiday were manageable.

Chokepoints

mukilteo hit-and-run fatal crash...

Jason Sutich

All lanes of southbound SR 525 reopen in Mukilteo after fatal hit-and-run motorcycle crash

All lanes of southbound SR 525 are fully blocked south of Beverly Park Road in Mukilteo following a fatal hit-and-run collision on Tuesday.

8 hours ago

Deception Pass SR 20 closures...

Chris Sullivan

19 days of closures to start Monday on SR 20 near Deception Pass

WSDOT will activate temporary traffic signals on SR 20 at Campbell Lake Road. They will allow one direction of travel through the construction zone for 19 days.

9 hours ago

Denny Way...

Paola Tristan Arruda, KIRO 7 News

Traffic patterns have changed on Denny Way as part of Route 8 project

One of Seattle’s busiest corridors has entered the final phase of a project designed to bring a new bus-only lane to Denny Way.

10 hours ago

bellevue road closures...

MyNorthwest Staff

Drivers beware: Road closures hit I-405 in Bellevue this week

Drivers heading through Bellevue this week will want to plan ahead.

22 hours ago

Amtrak...

James Lynch

Amtrak service between Seattle and Portland suspended this week

Amtrak service between Seattle and Portland is suspended through Friday due to a track obstruction caused by an earlier warehouse fire.

24 hours ago

seattle traffic...

Nate Connors

Major sports events, full closure on I-405 will make for very busy Seattle commute all weekend

This weekend around the Seattle area might go down as one of the busiest of the summer for the Washington State Department of Transportation.

4 days ago

WSDOT working hard to clear landslide blocking portion of I-5