‘30 truckloads from the finish line’: West Seattle Bridge reopening jeopardized by concrete strike

Feb 14, 2022, 5:10 AM | Updated: 9:20 am

West Seattle Bridge...

A vantage point on the West Seattle Bridge from Beacon Hill. (Flickr)

(Flickr)

The West Seattle Bridge has been closed since March 2020, and while the bridge was originally timed for reopening in June 2022, city leaders are concerned that the materials needed for repair are being throttled by Teamsters 174’s strike with the region’s concrete suppliers.

In a news conference last week, Seattle Mayor Bruce Harrell and King County Executive Dow Constantine marked Feb. 20, 2022, as the “drop dead” date for delivery resumption of SDOT’s concrete supply before West Seattle Bridge repairs are delayed.

Pressure mounts in concrete strike as King County offers $35 million bargaining chip

Mayor Harrell pointed out that specialized concrete blocks are required to hold the bridge’s steel cables for support and strength, and the relevant materials requests are due by Feb. 20 to maintain a repair schedule at the current 60 hours a week schedule.

“We are just 245 yards – fewer than 30 truckloads – from the finish line. I call on concrete suppliers to reach agreement with Teamsters Local 174 as soon as possible to ensure completion of the West Seattle Bridge repair is as scheduled,” Councilmember Lisa Herbold wrote in a news release.

Herbold noted that the West Seattle Bridge repair is an “emergency project” that, while in progress, cuts off businesses and workers on the West Seattle peninsula from the rest of the city. She adds that the bridge has been in use for 40 years, and the rest of the region’s transportation system is built around it.

As of Feb. 13, negotiations between Teamsters 174 and the six concrete suppliers remain at an impasse. Late last week, the union, which represents 300 striking workers, appeared on the steps of one the suppliers, Gary Merlino Construction, to demand talks continue after negotiations failed with a federal mediator in late January.

In a joint news release on behalf of Glacier, Stoneway, Salmon Bay, and Cadman, the suppliers named the event “an orchestrated media obstacle” and called on Teamsters 174’s secretary-treasurer to speak with “the Western Regional Director FMCS and [work] through her to arrange for a meeting as the Companies desired and communicated at the end of the mediation session of January 20.”

“We believe a controlled and professional negotiation with a federal mediator is the best way for the parties to arrive at a settlement,” the release stated.

In December, SDOT reported that it was in the final stages of the West Seattle Bridge’s repair, telling KIRO Newsradio that more than 91 tons of additional steel cable, carbon fiber, and the filling of concrete cracks with epoxy are among the final fixes to be made.

“Repair of the West Seattle bridge remains one of the City of Seattle’s highest priorities,” Mayor Harrell noted in a Feb. 9 news conference. “While the Seattle Department of Transportation, contractors, and community partners have worked tirelessly to keep the West Seattle Bridge reopening on track for mid-2022, this continued strike threatens to delay that schedule.”

“For an on-time opening, concrete companies and workers must return to mediation and reach a fair agreement – further delay and uncertainty is untenable for hundreds of thousands of neighbors across West Seattle, our city, and the entire region.”

KIRO Newsradio’s Chris Sullivan contributed to this report. 

MyNorthwest News

Everett apartment shooting...

MyNorthwest Staff

1 killed, 1 injured in shooting at south Everett apartment complex

The Snohomish County Sheriff's Office is searching for a suspect after two people were shot in a parking lot in south Everett.

2 hours ago

Seattle Public Schools...

KIRO 7 News Staff

Seattle Public Schools considers mergers as enrollment declines

Seattle Public Schools is considering school mergers as the district deals with declining enrollment and differences in learning conditions across its schools.

3 hours ago

US 2 Crash Monroe...

MyNorthwest Staff

US 2 blocked in both directions near Monroe after multi-vehicle collision

An early morning headache for drivers near Monroe. WSDOT says all lanes of US 2 are blocked in both directions near Monroe after a collision involving multiple vehicles.

3 hours ago

fish passage project...

Chris Sullivan

Massive fish passage project under I-90 in Factoria nearing its end

Eastbound I-90 drivers are close to getting their HOV lane back in Factoria. The fish passage project under the freeway is in its final months.

4 hours ago

oak harbor...

Lexi Herda, KIRO 7 News

Oak Harbor High School student trapped under car after being hit in marked crosswalk

An Oak Harbor High School student was rushed to the hospital after they were hit by a car and became trapped underneath the vehicle.

15 hours ago

3 - Tacoma Narrows Bridge...

KIRO 7 News Staff

Expect long PM commutes until further notice on the Tacoma Narrows Bridge

Drivers who use the Tacoma Narrows Bridge (SR 16) to Gig Harbor should expect longer nighttime commutes due to construction work.

16 hours ago

‘30 truckloads from the finish line’: West Seattle Bridge reopening jeopardized by concrete strike