CHOKEPOINTS

Massive fish passage project under I-90 in Factoria nearing its end

Oct 27, 2026, 5:00 AM | Updated: 4:02 pm

Eastbound I-90 drivers are close to getting their HOV lane back in Factoria. The fish passage project under the freeway is in its final months.

The lane has been closed for several years as the Washington State Department of Transportation (WSDOT) undertook one of its most complex fish passage projects to date. The state was tasked with replacing an old concrete culvert that was more than 50 feet below the freeway. It was greatly restricting fish passage in Sunset Creek.

Nearly all the work above the creek is done, and the eastbound I-90 HOV lane should reopen before the end of the year.

“Electrical and ITS work in the median, guardrail striping, final cleanup, and we have a lot of final planting to go through as well,” project engineer Seth Belknap said. “As of right now, the goal is to have the eastbound HOV lane opened up and return to the original configuration by the end of the year.”

So we’re almost there.

Work in the creek will last a few more months. The project might actually wrap up a few months ahead of schedule.

“We’ll have final — what we call punch list work — that is being worked on now and will take us through potentially January or February, but we anticipate being done in Quarter 1 of 2027,” Belknap said.

2-- fish passage project

An image taken about a month ago shows the new streambed stretching about 975 feet beneath four new bridges for the I-90 fish passage project. (Photo courtesy of WSDOT)

Fish passage project adds 4 bridges and nearly 1,000 feet of streambed

The original schedule had work going through the summer of next year.

The contractor has really accomplished a lot in the three-plus years of construction.

“We’ve constructed four new bridges: two across the eastbound and westbound I-90, and SE 36th St. and E Gateway as well,” Belknap said.

3 fish passage project

A fish spotted in the stream in summer 2025, before bridge work began on Eastgate Way. The project team counted 59 juvenile coho salmon and cutthroat trout at the location. (Photo courtesy of WSDOT)

The project also created nearly 1,000 feet of streambed to replace the culvert.

“Underneath the bridges, we’ve constructed retaining walls that allowed us to delineate the path for removing the old concrete culvert and constructing a new streambed with habitat features down below,” Belknap said.

Workers had to dig down over 50 feet to excavate the streambed. Now we will wait and see if any fish return to the creek.

The project price tag is over $100 million.

Chris Sullivan is a traffic reporter for KIRO Newsradio. Read more of his stories here. Follow KIRO Newsradio traffic on X.

Chokepoints

SR 18...

Nate Connors

WSDOT’s weekend itinerary includes a full closure of eastbound SR 18

The fall weather is beginning to slow some projects around the region, with many dependent on dry weather conditions.

1 day ago

port of seattle tsa...

Luke Duecy

Thanksgiving travel at SEA airport: TSA shares security tips, food rules, and craziest items found in carry-on

Thanksgiving travel is getting underway, and the TSA is preparing for a busy week at the Seattle-Tacoma International Airport (SEA).

2 days ago

wa freezing fog commute...

Jason Sutich

Freezing fog in parts of WA prompts morning commute warnings

A thick blanket of fog covered the greater Seattle area Friday morning, slightly reducing visibility for drivers’ morning commute.

2 days ago

Skagit County...

Chris Sullivan

‘Welcome to Skagit County’ sign sits miles inside Skagit County. Here’s why

Why is there a “Welcome to Skagit County” sign on a road already inside Skagit County? The answer has to do with where Mount Vernon ends.

3 days ago

Mason county mudslide us 101...

Jason Sutich

US 101 fully reopens in Mason County after a mudslide covered highway

US 101 in Mason County has fully reopened after a mudslide covered the highway with debris Wednesday morning.

4 days ago

Young driver seriously hurt, facing reckless driving charges in fiery I-5 crash near Kent...

James Lynch

14-year-old driver injured after van crashes in I-5 construction zone

A 14-year-old was behind the wheel of a van that sped into a southbound I-5 construction zone near SR 516 around 12:30 a.m. on Wednesday.

4 days ago

Massive fish passage project under I-90 in Factoria nearing its end