1-inch RapidRide G Line error costs Seattle $650,000 to fix

Apr 7, 2026, 8:48 AM

rapidride g line seattle...

Passengers wait at a Madison Street RapidRide station as a King County Metro G Line bus approaches. (Photo courtesy of the City of Seattle)

(Photo courtesy of the City of Seattle)

The City of Seattle is paying $650,000 to fix a bus line error along the RapidRide G Line.

Seattle Department of Transportation (SDOT) crews removed three orange steel plates that had lifted buses by approximately one inch and repaved the short sections of the roadway along Madison Street where the plates were initially placed.

Those orange plates were a stopgap solution to properly serve riders who use wheelchairs and walkers, as the original construction for the three center-road bus stops along King County Metro’s RapidRide G Line were roughly an inch too high when it first opened in 2024.

The $650,000 construction fix is expected to come from a $144.3 million construction project, which paid for nine new buses, built 8 miles of sidewalks, repaved the road, and replaced or upgraded more than 40 traffic signals, according to The Seattle Times.

The affected stops were Stops 104, 105, and 124. Stop 104 is on Madison Street between Terry and Boren Avenues, while Stop 105 is on Madison Street between Summit and Boylston Avenues, and Stop 124 is on Madison Street at E. Union Street and 12th Avenue E.

An SDOT spokesperson told The Seattle Times the specific bus platforms were “slightly too high for bus ramps to extend properly.” If the platform height is even slightly off, riders using wheelchairs, walkers, or experiencing other mobility issues can’t get on or off the bus.

The RapidRide G Line, which opened in 2024, connects Madison Valley, Capitol Hill, First Hill, and Downtown Seattle.

Chokepoints

construction roadways weekend...

Paola Tristan Arruda, KIRO 7 News

Prepare for another weekend of major construction on three roadways

Travelers in the Puget Sound region should prepare for delays and road closures this weekend as construction takes place across I-405, SR 99, and I-5.

10 hours ago

A photo of the northbound I-5 closure near Everett. (Photo courtesy of the Washington State Departm...

Jason Sutich

25-year-old man arrested after climbing, hanging from I-5 overpass near Everett

A 25-year-old man was arrested after climbing and hanging from an I-5 overpass near Everett, prompting officials to shut down all lanes in the area.

1 day ago

tiger mountain sr 18 blocked...

Jason Sutich

All lanes of SR 18 reopen after semi-truck, motorcycle collision near Tiger Mountain

All lanes of SR 18 near Tiger Mountain have reopened after a semi-truck and motorcycle collision.

1 day ago

link light rail sound transit west seattle expansion delay...

Chris Sullivan

West Seattle light rail expansion delayed another 3 years

This is not what West Seattle transit riders wanted to hear. Light rail service to the neighborhood has been delayed again.

1 day ago

bellevue i-405 i-90 ramp close...

Jason Sutich

NB I-405 ramp to EB I-90 in Bellevue reopens hours after semi carrying garbage overturned

The northbound I-405 ramp to eastbound I-90 in Bellevue is fully blocked after a semi-truck carrying garbage overturned on the roadway.

2 days ago

Sound Transit budget deficit delays...

Chris Sullivan

Sound Transit looks to double cost of property acquisition, construction support services for West Seattle expansion

Sound Transit said it needs another $765 million to acquire property and prepare for the link extension to West Seattle, but the overall budget won't change.

2 days ago

1-inch RapidRide G Line error costs Seattle $650,000 to fix