CHOKEPOINTS

WSDOT taking bridge ‘down to bare metal’ with SB I-5 closure in Arlington

Jun 22, 2021, 5:08 AM | Updated: 6:42 am

Bridge...

The paint on the 88 year old Stilliguamish River Bridge is in need of serious attention. (WSDOT

A five-month closure of the southbound I-5 bridge over the Stillaguamish River begins this week in Arlington.

Seattle to have busy construction summer ahead in Montlake

How long does it take to give an 88-year-old a good makeover?  If you’re a steel truss bridge, the answer is about five months.

The southbound I-5 bridge in Arlington is going to be closed for about five months. The closure is expected to happen shortly after midnight early Wednesday morning. The 607-foot bridge needs a serious paint job. It’s the paint that helps preserve the steel.

“We’re going to be removing the old paint, taking the entire bridge back down to the very bare metal and then re-applying paint on all those exposed areas and making sure that we’re protecting and preserving this bridge for years to come,” said Jordan Longacre with the Washington Department of Transportation.

The plan is to wrap the bridge first to prevent any debris from getting into the river below.

“Everything that is taken off the bridge is then captured in this containment system and then hauled away and disposed of properly,” Longacre said.

Starting Wednesday morning, all southbound drivers are going to be diverted into the northbound lanes over the river. If you’ve lived here awhile, you might remember doing this crossover in 2014 when the southbound bridge deck was replaced. There is a large strip of concrete in the median of the freeway on either side of the bridge to accommodate the transition.

“Thankfully, we’re able to rely on some of the things that were already put in place for the previous cross-over, and we’re hoping that drivers are able to navigate that just as easily as they did before,” Longacre said.

West Seattle High-Rise Bridge clears major hurdle on road to repair

The transition will likely catch some drivers by surprise early Wednesday, but Longacre doesn’t expect too much of an issue.

“We have barriers and barrels and striping all in place that drivers will see, even before they approach the bridge,” he said.

Two lanes in each direction will be open during the five month closure. The lanes will be reduced in width, from 12 feet to 11 feet. The speed limit in the area will also be reduced to 55 miles per hour.

Drivers need to plan for extra congestion, especially over the summer weekends.

“We want to make sure that we really bring this bridge back to its original state, and that we’re able to preserve it,” Longacre said. “The way to do that is to take the time needed to do it.”

Check out more of Chris’ Chokepoints.

Chokepoints

ritzville i-90 closed visibility...

Jason Sutich

I-90 in Ritzville reopens after dust storm caused multiple collisions

I-90 in Ritzville has reopened after both directions were blocked Friday due to multiple collisions.

16 hours ago

super load marysville...

Chris Sullivan

Super load stuck on I-5 south in Marysville should move tonight

A truck carrying a massive pre-fab building has been parked along the southbound I-5 ramp at 88th St. in Marysville for three days.

22 hours ago

closure (1)...

MyNorthwest Staff

I-5 reopens in both directions between Maytown and Tumwater

I-5 has reopened in both directions in Thurston County at milepost 97, KIRO Newsradio confirmed.

23 hours ago

oyster run anacortes...

Nate Connors

43rd annual Oyster Run returns this weekend in Anacortes

The Oyster Run welcomes thousands of motorcyclists to Skagit County by Figaldo Bay. It's loud, it's proud, and it takes over Anacortes this time each year.

2 days ago

sounder train shoreline...

MyNorthwest Staff

All S Line trains stopped after woman hit in SODO

All Sound Transit S Line trains have been stopped after a woman was hit in SODO Thursday.

2 days ago

Pinehurst Station light rail...

Chris Sullivan

Sound Transit to open new light rail station 5 years ahead of schedule

Sound Transit isn't known for being on time or on budget with its light rail projects, but it's about to open a new station way ahead of schedule.

2 days ago

WSDOT taking bridge ‘down to bare metal’ with SB I-5 closure in Arlington