Bertha’s work under Seattle’s viaduct has ‘no adverse influence’ on the aging structure

May 9, 2016, 6:43 AM | Updated: 8:27 am

Crews monitored the Alaskan Way Viaduct as Bertha tunneled underneath the aging structure. The stat...

Crews monitored the Alaskan Way Viaduct as Bertha tunneled underneath the aging structure. The state reports tunneling did not have any adverse impacts on the viaduct and reopened it days ahead of time. (WSDOT)

(WSDOT)

Bertha performed as advertised when the tunnel boring machine plunged under the Alaskan Way Viaduct, allowing the state to reopen the roadway four days ahead of schedule.

Engineers determined that tunneling under the viaduct did not cause any issues with the aging structure. Todd Trepanier with the Washington State Department of Transportation (WSDOT) says that is because the tunneling contractor was able to maintain control of the ground as crews continued excavation.

“This early opening is possible due to [Seattle Tunnel Partners’] ability to control the ground during this tunneling in this area, having no adverse influence on the viaduct structure,” he said.

Related: Seattle tunnel progress a major contrast to past problems

After about 318 feet, the state decided it was safe to reopen the viaduct.

Trepanier says Bertha began to perform as expected once it hit more solid soil.

But Travis Phelps with WSDOT admits there was some concern.

“With Bertha coming out of the repair shop and then straight to tunneling under the viaduct, I think a lot of us had some nervous tension,” he said. However, Phelps says the department is pleased the contractor reached this point.

A lot of people on social media are questioning whether this was a case of over-promising so Seattle Tunnel Partners and WSDOT could have a much-needed PR win on the project. There were also questions of whether Seattle Tunnel Partners would get some sort of bonus out of this – which it does not, according to Trepanier.

Bertha still has about 7,800 feet to go before the machine’s journey ends at the north portal.

Chokepoints

mukilteo hit-and-run fatal crash...

Jason Sutich

All lanes of southbound SR 525 blocked in Mukilteo after fatal hit-and-run motorcycle crash

All lanes of southbound SR 525 are fully blocked south of Beverly Park Road in Mukilteo following a fatal hit-and-run collision on Tuesday.

34 minutes ago

Deception Pass SR 20 closures...

Chris Sullivan

19 days of closures to start Monday on SR 20 near Deception Pass

WSDOT will activate temporary traffic signals on SR 20 at Campbell Lake Road. They will allow one direction of travel through the construction zone for 19 days.

2 hours ago

Denny Way...

Paola Tristan Arruda, KIRO 7 News

Traffic patterns have changed on Denny Way as part of Route 8 project

One of Seattle’s busiest corridors has entered the final phase of a project designed to bring a new bus-only lane to Denny Way.

3 hours ago

bellevue road closures...

MyNorthwest Staff

Drivers beware: Road closures hit I-405 in Bellevue this week

Drivers heading through Bellevue this week will want to plan ahead.

15 hours ago

Amtrak...

James Lynch

Amtrak service between Seattle and Portland suspended this week

Amtrak service between Seattle and Portland is suspended through Friday due to a track obstruction caused by an earlier warehouse fire.

17 hours ago

seattle traffic...

Nate Connors

Major sports events, full closure on I-405 will make for very busy Seattle commute all weekend

This weekend around the Seattle area might go down as one of the busiest of the summer for the Washington State Department of Transportation.

4 days ago

Bertha’s work under Seattle’s viaduct has ‘no adverse influence’ on the aging structure