Traffic alert: WSDOT postpones 5-day closure, some weekend work due to weather

May 15, 2025, 5:00 AM | Updated: 3:24 pm

WSDOT shutdowns I-405Renton to Bellevue Widening and Express Toll Lanes Project...

WSDOT is rolling out major shutdowns, including reducing lanes on I-405 south for the I-405/Renton to Bellevue Widening and Express Toll Lanes Project. (Image courtesy of WSDOT)

(Image courtesy of WSDOT)

Drivers will want to plan ahead as the Washington State Department of Transportation (WSDOT) is rolling out several closures over the weekend and spilling into next week. However, WSDOT announced some closures have been postponed due to weather.

State Route 18 closure at I-90 postponed

Drivers along State Route 18 (SR 18) at I-90 will see big changes following a 5-day closure at this busy interchange near the city of Snoqualmie. The Washington State Department of Transportation (WSDOT) decided on this unprecedented closure to tackle a number of projects at once, as opposed to taking a series of weekend closures to address the next phase of the I-90/SR18 – Diverging Diamond Interchange Project sometime after Memorial Day.

Crews will install new drainage and electrical crossings, pave the new roadway, and construct concrete islands to form the southern part of the new I-90/SR 18 diverging diamond interchange.

However, work on the left turn pocket for traffic from westbound SR 18 onto Southeast 104th Street, as well as the signalized U-turn south of I-90 (which will allow eastbound SR 18 traffic to head westbound toward Auburn), has been postponed for rain. Both of these features will be operational when SR 18 reopens on Wednesday, May 21.

During the closure, there will be no access on SR 18 underneath the I-90 overpass. Drivers will be able to access Snoqualmie Parkway from westbound I-90 only, and accessing SR 18 will only be open from eastbound I-90. Detours will be in place.

This extended closure starts Thursday, May 15 at 9 p.m. to Wednesday, May 21 at 5 a.m.

Lane and ramp closures on I-405 in Renton postponed

The one-lane reduction on southbound I-405 has also been delayed due to weather. Eventually, crews will close one lane between Northeast 44th Street and Northeast 30th Street while they work to realign and repave the Northeast 30th Street on,  and off-ramps. This work will fully close the on-ramp to southbound I-405 and the off-ramp from southbound I-405 at Northeast 30th Street.

Closures begin Friday at 11 p.m. to Monday, May 19, at 4 a.m. Detours will be in place. Drivers should expect heavy delays through Renton, with added freight traffic due to the closure at the SR 18 and I-90 interchange.

State Route 529 closures on the Snohomish River Bridge

Unlike the past couple of weekends, there will be 12-hour closures on Saturday and Sunday on northbound State Route 529 (SR 529) for bridge maintenance, including repair to bridge girders. This work will not affect southbound SR 529. Daily closures are scheduled between 6 a.m. to 6 p.m.

Westbound I-90 closure between Mercer Island and Seattle

All westbound lanes on I-90 will close between Island Crest Way on Mercer Island to Rainier Avenue South in Seattle for routine maintenance inside the Mercer Tunnel and the Mount Baker Tunnel. Routine maintenance typically includes fire suppression testing, testing emergency systems, replacing bulbs, and overall cleaning.

Westbound I-90 lanes will begin closing Friday, May 16, at 8:30 p.m., with all lanes closed by 10 p.m. All ramps along this route will also close, with all lanes and ramps reopened by 6 a.m., Saturday, May 17. This leaves westbound SR 520 as the only route across Lake Washington during this closure.

Northeast 85th Street closure at I-405 in Kirkland

Both directions of Northeast 85th Street will fully close between Kirkland and Totem Lake to allow WSDOT crews to perform a number of big projects, including demolishing the old bridges and noise walls, repaving ramps, and installing new gas lines and a waterline.

The closure—between 114th Avenue Northeast (Kirkland) and 120th Avenue Northeast (Totem Lake)—begins Friday, May 16, at 11 p.m. to Monday, May 19, at 5 a.m.

Click here to see the detours this weekend.

Nate Connors is a traffic reporter for KIRO Newsradio. Follow him on X. Read more of his stories here. Submit news tips here.

Chokepoints

Flying for the holidays? SEA airport ranks No. 3 for fewer travel disruptions...

Regan Gallo-Fenz

Flying for the holidays? SEA Airport ranks No. 3 for fewer travel disruptions

If you're worried about flying out of Seattle-Tacoma International (SEA) airport for the holidays, a new consumer report may ease your mind. SEA ranks third among the best airports for avoiding travel disruptions, according to a ConsumerAffairs report. By utilizing U.S. Department of Transportation data from 2024 and 2025, the study ranks small, medium, and large airports, with Seattle in the large category. 

7 hours ago

New partial joint installed on Tacoma Narrows Bridge...

Lexi Herda, KIRO 7 News

New partial joint installed on Tacoma Narrows Bridge

Some good news for drivers who regularly use the Tacoma Narrows Bridge. The Washington State Department of Transportation says the new partial joint has been installed on the aging structure.

10 hours ago

US 2 Crash Monroe...

MyNorthwest Staff

US 2 reopens after multi-vehicle collision shuts down all lanes for nearly six hours

An early morning headache for drivers near Monroe. WSDOT says all lanes of US 2 are blocked in both directions near Monroe after a collision involving multiple vehicles.

19 hours ago

fish passage project...

Chris Sullivan

Massive fish passage project under I-90 in Factoria nearing its end

Eastbound I-90 drivers are close to getting their HOV lane back in Factoria. The fish passage project under the freeway is in its final months.

20 hours ago

3 - Tacoma Narrows Bridge...

KIRO 7 News Staff

Expect long PM commutes until further notice on the Tacoma Narrows Bridge

Drivers who use the Tacoma Narrows Bridge (SR 16) to Gig Harbor should expect longer nighttime commutes due to construction work.

1 day ago

Amtrak...

Chris Sullivan

Amtrak opens new Seattle maintenance facility ahead of 2027 schedule

Amtrak has cut the ribbon on its new 100,000-square-foot maintenance facility in SODO, opening a building originally scheduled to debut in 2027.

5 days ago

Traffic alert: WSDOT postpones 5-day closure, some weekend work due to weather