CHOKEPOINTS

Will I-90 be closed for Sound Transit light rail construction?

Jan 24, 2019, 7:33 AM | Updated: 2:00 pm

Sound Transit is nearing 50 percent completion of its light rail expansion to the Eastside, but will the agency need to shut-down I-90 to complete the link to Mercer Island?

RELATED: City reports massive increase in biking as Viadoom begins

KIRO Radio morning host Dave Ross brought this question to me a few weeks ago. There is a giant gap in the flyover connection where the light rail tracks move from the center of I-90 to Bellevue Way, just across the East Channel Bridge. He was concerned about a potential closure of the freeway to connect the two sides.

I met with Rachelle Cunningham of Sound Transit at the site to discuss the upcoming schedule.

“The main span is going to be completed in two segments, and they are going to meet in the middle, right over the freeway,” she said. “We’re very close to finishing the first span.”

That should happen in March. Sound Transit is using what it calls a “traveler” to build the elevated track. The machine sits at the end of the span and pushes forward as it lays the concrete.

“It moves about 12 feet at a time,” Cunningham said. “It pours the concrete, and it cures and then it will move out again.”

When it reaches the end — just over westbound lanes of I-90 — the contractor will need just one night to remove the traveler so it can be moved to the other side to start work on the connection.

“They’ll move out to the middle and then join, but to do that we will need to close the lanes of traffic once, overnight, in March, and then this will all be completed in November,” Cunningham said.

She also said it will take one more night closure in November to finish the job. Only two night-time closures to complete the span, under the current schedule, sounds more than manageable for putting a train track over the freeway.

This project is going to make big strides in 2019. Track is already being laid along the route, and it will start going on the floating bridge this summer. Station construction is also underway in a few locations, and Cunningham said the timing looks good.

“Things are on schedule,” she said. “Things are going really well. It’s on budget, it’s on schedule, and we’re just plugging ahead.”

Chokepoints

Tacoma Narrows Bridge (4)...

Nate Connors

WSDOT completes Tacoma Narrows Bridge repairs one week early

Pierce County commuters were handed some good news when WSDOT announced that it had completed repairs on the Tacoma Narrows Bridge.

2 days ago

Photo: Port Townsend/Coupeville ferry routes have been canceled....

Nate Connors

Mukilteo/Clinton ferry service to end early again for repairs

Mukilteo/Clinton ferry service will end early again Friday night as crews finish emergency repairs at the Mukilteo terminal.

2 days ago

wsdot vehicle fire...

MyNorthwest Staff

Semitruck carrying bananas catches fire, blocks lanes on southbound I-5 in Tacoma

A massive commercial vehicle fire is blocking lanes on southbound I-5 in Tacoma.

2 days ago

SR 167 crash...

MyNorthwest Staff

1 killed, 1 in custody after crash on SR 167 in Auburn

Southbound SR 167 is blocked in Auburn after a deadly three-car crash, according to Washington State Patrol Trooper Rick Johnson.

2 days ago

Sound Transit light rail...

Julie Berg, KIRO 7 News

Sound Transit launches pilot program allowing pets on light rail and buses

Sound Transit has launched a limited-duration pet policy pilot program allowing pets aboard transit services under updated guidelines.

2 days ago

revive I-5 tolls I-405 commute...

Julie Berg, KIRO 7 News

Puget Sound travelers will face major disruptions on I-5 and I-405 this weekend

Travelers in the Puget Sound region face major highway shutdowns Halloween weekend due to two major construction projects.

3 days ago

Will I-90 be closed for Sound Transit light rail construction?