I-90 work marks milestone for light rail to Bellevue

Apr 2, 2019, 6:03 AM | Updated: 10:51 am

light rail...

(AP)

(AP)

One of the missing links in the construction of the light rail project to Bellevue is the section where the tracks will go over the westbound lanes of I-90 to Bellevue Way.

RELATED: Night closures of I-90 in Bellevue for light rail work

Half of the bridge connecting the tracks from the middle of I-90 to Bellevue Way is now complete, and Monday night, westbound I-90 was closed to remove the “form traveler” that built the bridge. Sound Transit’s Rachelle Cunningham said the “form traveler” builds the structure as it moves, which eliminated the need for a series of freeway closures.

“It moves twelve feet at a time,” she said. “The traveler will move out, pour the concrete, it cures, and then it moves out again. It basically spits it (the concrete) out in front of it.”

That “form traveler” will now be moved to the side of the elevated structure near Bellevue Way, and start building to middle to complete the bridge. You can expect to see some lane and ramp closures in the same area a few more nights this week. The “form traveler” should finish the second half of the bridge in November, which will also require some overnight closures of I-90.

Cunningham said this method of construction just made sense because of the limited space in the area and the freeway below.

“There’s not really any room on the freeway to put the supports that we have over I-405 where they have the form work, and they’re building it that way,” she said. “This method of construction allows us to do it without disrupting the traffic.”

Light rail to Bellevue is now more than 50-percent complete, and it is still on schedule to open in 2023, with the extension to Redmond coming a year later.

Youwill see track being laid on the floating bridge as early as this month.

Chokepoints

Puyallup railroad...

MyNorthwest Staff

Puyallup railroad crossing arms stuck in down position

The railroad crossing arms in downtown Puyallup are stuck in the down position.

14 hours ago

military vehicle I-5 Tacoma...

Frank Sumrall

All lanes reopened after civilian car hits military vehicle on northbound I-5 near Tacoma Mall

A crash involving a military vehicle occurred on northbound I-5 in Tacoma Friday morning.

15 hours ago

traffic weekend closure...

Paola Tristan Arruda, KIRO 7 News

Weekend traffic headaches ahead: Major closures planned on I-405, SR 520/Montlake, and SR 99

Drivers traveling around the Puget Sound region this weekend should prepare for yet another weekend of delays as several major road projects overlap across King County.

17 hours ago

I-5 off-ramp DUI SR 18...

Frank Sumrall

Northbound I-5 off-ramp to SR 18 reopens after 4.5-hour DUI closure

The northbound I-5 off-ramp to eastbound SR 18 reopened Thursday morning after a single-car collision blocked the roadway for nearly 4.5 hours.

2 days ago

WA driver's license (1)...

Chris Sullivan

Getting a WA driver’s license is about to get a lot harder

There are major changes coming to the requirements for new drivers and license applicants over the next few months.

2 days ago

SR 99 snohomish county wsdot...

MyNorthwest Staff

WSDOT proposes $800M transformation of SR 99 corridor in Snohomish County

The Washington Department of Transportation proposed several improvements to a stretch of SR 99 — a seven mile corridor from Lynnwood toward Everett.

3 days ago

I-90 work marks milestone for light rail to Bellevue