CHOKEPOINTS

More trees come down as Sound Transit builds light rail toward Redmond

Oct 27, 2020, 5:36 AM

Drivers on 520 have probably already noticed, but the first signs of Sound Transit’s Link light rail expansion from Microsoft to downtown Redmond are now visible.

The elevated tracks along 520 have been obvious for months. They run right next to the eastbound lanes of the freeway to what Sound Transit calls the Redmond Technology Station, near the Microsoft campus. Sound Transit has now started clearing the path for the extension all the way to downtown Redmond.

“Removing trees, demolishing some structures and relocating some utilities, really preparing the surface for the big construction next year,” Sound Transit’s Rachelle Cunningham said about the project.

The most obvious signs of this work are the loss of trees along the freeway. Loggers have started taking them down near Marymoor Park.

“It’s unfortunate that any time we build something like this, trees do have to come down,” Cunningham said. “The good news is we do replace them with a significantly larger number of trees. In this case, in Redmond, about 3,000 trees are going to be coming down, but we promise to replace them with 12,000.”

This is the same way Sound Transit cleared the path for the Lynnwood light rail extension along I-5. More than 5,000 trees were removed for that project, and Sound Transit will replace them with nearly 21,000.

“Tearing things down before you can build them up,” Cunningham said of the process.

Sound Transit is doing a lot of environmental work on the Redmond extension. It is restoring more than 500 feet of Bear Creek, and will remove a creosote treated railroad trestle, other debris, and fish-blocking culverts.

A tour of the recently completed Bellevue Sound Transit tunnel

The 3.5-mile light rail extension from the Microsoft campus to downtown Redmond will include two stations, one at Marymoor Park and another in downtown Redmond. There will be a 1,400 stall parking garage added at Marymoor Park.

The line is still expected to open in 2024, a year after the line to Bellevue opens. Sound Transit said it will only take 18 minutes from downtown Redmond to downtown Seattle.

Check out more of Chris’ Chokepoints.

Chokepoints

I-90...

Nate Connors

WSDOT announces temporary closure of westbound I-90 Wednesday

WSDOT announced a Wednesday morning closure of all westbound I-90 lanes near milepost 52 at Snoqualmie Pass.

7 hours ago

I-5 crash...

MyNorthwest Staff

Crash blocking two right lanes on northbound I-5 in Seattle

A crash is blocking the two right lanes and the HOV lane on northbound I-5 in Seattle.

8 hours ago

larch madness parking leaves changing...

Chris Sullivan

‘Larch Madness,’ more like bad parking madness as people chase view of changing leaves

You're running out of time to catch "Larch Madness" along SR 20 in the North Cascades. But if you do head up there over the next few days, don't act like a fool.

19 hours ago

SR 164 enumclaw fatal crash...

Jason Sutich

Two drivers killed in head-on crash on SR 164 near Enumclaw

Two people died after a collision on SR 164 near Enumclaw that closed the road in both directions for more than four hours early Monday morning.

2 days ago

montlake pedestrian bridge sr 520...

Nate Connors

Montlake pedestrian bridge closes for a week at SR 520

Pedestrians and bicyclists at Montlake will need to navigate a detour crossing over SR 520 for a full week, beginning Monday, Oct. 19, at 7 a.m.

2 days ago

Sound Transit budget deficit delays...

Michael Strite

Sound Transit to host community forum after Ballard light rail delayed to 2042

Sound Transit is encouraging Seattle residents to speak up about the proposed light rail extension to the Ballard neighborhood.

2 days ago

More trees come down as Sound Transit builds light rail toward Redmond