CHOKEPOINTS

Everett’s Edgewater Bridge to reopen April 28 after 18 months of construction

Apr 14, 2026, 5:00 AM | Updated: Apr 15, 2026, 7:42 am

Everett’s Boulevard Bluffs neighborhood has been cut in half for nearly 18 months as an 80-year-old bridge over a ravine has been demolished and rebuilt. The project wraps in two weeks, and neighbors are excited.

People living along Everett’s Boulevard Bluffs have been waiting for this project to come and go for a long time. The bridge, built in 1946, was supposed to be replaced years ago, but there were problems with the bidding process. Then came the pandemic.

The project didn’t begin until late 2024. It was supposed to take about a year.

Heavy rains, damaged equipment, and an old wooden bridge unearthed during excavation added several more months to the project, but on April 28, the Edgewater Bridge will reopen.

Sid and Judy have lived in this neighborhood for 44 years.

“It needed doing,” Sid told me. “It’s going to be better than it was. So, you know, we’re OK with it.”

Judy called it a “hassle.”

The bridge is less than 500 feet long, but it is a lifeline for the community. The closure has cut off the walking paths and access between Everett and Mukilteo. The detour from end to end is about 10 miles.

“We go often to Mukilteo, and it would be a five-minute drive to just about anywhere,” Sid said. “Now it’s like 20 minutes or so.”

But it hasn’t all been negative. Judy told me they have some new neighbors.

“We’ve had a lot of coyotes and deer in our yard that I think we’re displaced by what happened, and that’s been a lot of fun to watch,” she said. “There’s an upside to everything, right?”

Bridge officially opens in two weeks

There will be a ribbon cutting on Tuesday, April 27, at 3:30 p.m., and people will be invited to walk across the bridge. It will reopen to car traffic at the end of the workday on April 28.

Everett City Engineer Tom Hood told me earlier this year that he is incredibly thankful for the neighborhood’s patience.

“Our first message is empathy with the neighbors that are affected by this,” Hood said. “The closer the people live to the bridge, the more affected they are, obviously, with the detour route and things like that, and so that is never lost on us.”

The new bridge includes wider sidewalks and new bike lanes in each direction. Those sidewalks won’t be open until all the finishing touches are in place. That work includes final striping, barriers, and lighting.

Chris Sullivan is a traffic reporter for KIRO Newsradio. Read more of his stories here. Follow KIRO Newsradio traffic on X.

Chokepoints

3 ground stop...

Julia Dallas

Ground stop lifted as hundreds of flights canceled at SEA; officials cite ‘major engineering defect’

A ground stop has been issued for all airports nationwide by the Federal Aviation Administration (FAA).

2 days ago

Orcas Island Ferry...

Julia Dallas

Gov. Ferguson, WSF working with San Juan County on Orcas Island ferry terminal repairs

San Juan County has issued a declaration of a state of emergency due to damage at the Orcas Island ferry terminal.

2 days ago

Federal Way collision northbound I-5 two lanes blocked...

Regan Gallo-Fenz

All NB I-5 lanes reopen near Federal Way after collision

The two right lanes of northbound I-5 in Federal Way have reopened following a collision just south of State Route 18 near milepost 141.

2 days ago

sounder train dog attack...

Chris Sullivan

Dog attack on Sounder train 2 weeks after pet policy change

Earlier this week, a dog attack occurred on a Sounder train, where a dog attacked a service dog.

2 days ago

Seattle Freeways tailgaters...

Charlie Harger

Harger: Turn signals, tailgaters, and the 5 most annoying drivers on Seattle freeways

I drive to work in the dark, and I’m coming down the ramp from westbound Highway 18 onto northbound I-5. Wipers going. Coffee in the cupholder. A semi is barreling down the right lane, and there’s a car in front of me on the ramp.

2 days ago

seatac crash i-5...

KIRO 7 News Staff

NB lanes of I-5 in SeaTac reopen 7 hours after deadly multi-car crash

The northbound lanes of I-5 in SeaTac were closed for almost 7 hours, and traffic was backed up over a mile after a deadly multi-car crash on Thursday night.

2 days ago

Everett’s Edgewater Bridge to reopen April 28 after 18 months of construction