Realign99: The countdown to Seattle’s longest-ever highway closure

Nov 15, 2018, 12:45 PM

We’re quickly closing in on the closure of the Alaskan Way Viaduct, as workers begin preparing for what will be the longest highway closure in Seattle’s history.

RELATED: How traffic will work after Seattle’s SR 99 tunnel opens

Dubbed “Realign99” by the city, closures for the project begin Jan. 4, 2019, when the southbound off-ramp at South Atlantic Street will be shut down. Then, the big stuff kicks off when the viaduct closes for good on Jan. 11.

Before the new SR 99 tunnel is operational, Seattle will see roughly three weeks of closures to realign the highway into the tunnel. After the tunnel opens to drivers, it will take another two weeks to finish construction for the northbound off-ramp to Alaskan Way and South Dearborn Street.

The Realign99 checklist is extensive, with a good deal of work involving the tearing down of detour routes. Sections of SR 99 to the north and south of the tunnel that drivers use today are actually temporary detour roads that will need to come down before the tunnel opens

After those detours are removed, ramps that were buried need to be unburied.

“Years ago, Seattle Tunnel Partners built the on and off-ramps to the tunnel,” said WSDOT Deputy Administrator David Sowers, in a recent video breaking down the construction. “But those ramps were located in the footprint of where the detour now is — now that the detour is coming out, they will take all that material out, open those ramps up, and then make those connections into the tunnel.”

KIRO Radio’s Chris Sullivan was on-site at the tunnel Thursday morning to see for himself how things are coming along.

Today, the Alaskan Way Viaduct sees roughly 90,000 drivers a day, making for what’s sure to be some serious congestion in downtown Seattle once it shuts down for Realign99. During the closure period beginning Jan. 11, WSDOT asks that drivers shift travel times to avoid busy hours, bike or walk instead of driving, join a carpool, take public transit, or stay off the downtown roads altogether.

RELATED: SR 99 tunnel is built, so why can’t we use it yet?

Chokepoints

copper wire theft lighting lakewood...

Chris Sullivan

Wire theft knocks out more lighting along I-5 in Lakewood

Here we go again. Thieves who ripped wire from Washington State Department of Transportation electrical boxes impacted drivers in Lakewood earlier this week.

14 hours ago

othello crash sr 24...

MyNorthwest Staff

11 injured in work bus, semi-truck crash on SR 24 near Othello

At least 11 people were injured in a "critical incident" after a work bus and semi-truck collision on SR 24 near Othello Thursday morning.

17 hours ago

wa toll...

Chris Sullivan

Get ready, drivers: Puyallup to Lynnwood could cost $54 in tolls

We're less than a year from the expansion of the express toll lane system between Renton and Bellevue, marking the start of segmented tolling.

20 hours ago

revive I-5 tolls I-405 commute...

Nate Connors

Revive I-5 on Ship Canal Bridge to end 2 months ahead of schedule

WSDOT announced it has moved up Revive I-5's completion date to the weekend of Oct. 30, which is two months ahead of schedule.

1 day ago

train puyallup...

MyNorthwest Staff

Man in wheelchair killed after being hit by train in downtown Puyallup

Two people have been hit by a train in downtown Puyallup.

1 day ago

Snoqualmie Pass Closure...

MyNorthwest Staff

Westbound I-90 back open at Snoqualmie Pass after winter preparation

Westbound I-90 has reopened after a temporary closure at Snoqualmie Pass.

1 day ago

Realign99: The countdown to Seattle’s longest-ever highway closure