CHOKEPOINTS

Revive I-5 reaches halfway point in Seattle

Aug 4, 2025, 6:15 PM

ship canal bridge revive I-5...

Road crews work on the Ship Canal Bridge. (Photo: Feliks Banel)

(Photo: Feliks Banel)

Monday, August 4, marked the halfway point on the Washington State Department of Transportation’s (WSDOT) Revive I-5 project on Seattle’s Ship Canal Bridge.

A lot of work has been accomplished, and crews seem to be on pace to complete this section by Aug. 15, as projected.

So far, WSDOT contractors have removed the driving surface on about 900 feet of the two left lanes. They’ve also replaced the left half of five expansion joints and about 60 drains on the bridge.

The next two weeks will bring more repaving and drainage work.

Revive I-5 continues

On Friday, Aug. 15, all northbound lanes on I-5 will start closing around 9:30 p.m., leading up to the full closure. The mainline I-5 lanes will close near I-90 just before midnight. Drivers going downtown will need to exit at the Edgar Martinez Drive, Dearborn, James, or Madison streets exits.

People going north of downtown will be able to use the express lanes, which have remained open northbound since the beginning of this project. During the weekend-long closure that begins late on Aug. 15, the Columbia/Cherry on-ramp to the express lanes will be open to all drivers. Until early on Saturday, Aug. 16, that ramp remains HOV only.

Monday, Aug. 18, all northbound lanes on I-5 will reopen and remain free of closures until winter of 2026. That is when WSDOT will start this project again, this time blocking two right lanes across the Ship Canal Bridge.

With the 2026 FIFA World Cup in Seattle next summer, Revive I-5 will pause for a few weeks so all lanes on I-5 will be accessible when an estimated 500,000 fans from across the globe convene in Seattle.

In mid-July of 2026, after the World Cup, WSDOT will continue Revive I-5 where they left off, closing two right lanes on the Ship Canal Bridge through the fall. In 2027, get ready for this project to shift to the southbound lanes starting with the closure of two left lanes in winter and summer, followed by two right lane closures through the fall.

Nate Connors is a traffic reporter for KIRO Newsradio. Follow him on X. Read more of his stories here. Submit news tips here.

Chokepoints

on-ramp I-5 northbound Harvard Avenue E...

Chris Sullivan

Only northbound I-5 on-ramp between Mercer Street and U-District reopens early

The Harvard Avenue E on-ramp to northbound I-5 reopened to traffic about 4:45 a.m. Friday morning, about three days ahead of schedule.

2 hours ago

I-5 crash everett delays backup...

MyNorthwest Staff

Everett crash causes 7-mile backup, 40-minute delays on southbound I-5

A crash is causing a seven-mile backup and a 40-minute delay on southbound I-5 between Arlington and Everett.

1 day ago

WSDOT...

Chris Sullivan

From potholes to 9 million toilet flushes: WSDOT maintenance crews’ busy summer

The Washington State Department of Transportation (WSDOT) has about 1,500 maintenance workers who fall into that category.

1 day ago

copper wire theft wsdot cameras...

Chris Sullivan

Attempted copper wire theft knocks out WSDOT cameras, travel data for several days

WSDOT cameras and travel data were down for days due to a copper wire theft, affecting real-time traffic updates across Washington.

2 days ago

aurora avenue crash...

Frank Sumrall

Multi-car crash blocks Aurora Avenue early Wednesday morning

At least two cars were involved in an early morning crash Wednesday on Aurora Avenue N. that blocked multiple lanes.

2 days ago

EdmondsKingston...

Nate Connors

Washington State Ferries to suspend Edmonds/Kingston route

The Edmonds/Kingston ferry route will be suspended for railroad work.

3 days ago

Revive I-5 reaches halfway point in Seattle