300-foot section of SR 530 reopens after a month of flood repairs
Jan 21, 2026, 9:20 AM | Updated: 9:39 am
A side-by-side photo of the damage and repair work along SR 530. (Photo courtesy of the Washington State Department of Transportation)
(Photo courtesy of the Washington State Department of Transportation)
A 300-foot section of eastbound and westbound SR 530 between Rockport and Darrington was reopened on Tuesday after it sustained heavy damage during the December flooding.
Over the past month, the Washington State Department of Transportation (WSDOT) crews rebuilt the damaged section of an embankment that was washed away during the atmospheric river flooding, WSDOT announced.
During the repair efforts, WSDOT also repaved the roadway in addition to installing striping and guardrails.
SR 530 REOPENS
EB & WB SR 530 reopened between Rockport & Darrington Tues (1/20).Over the past month, crews rebuilt a 300-foot section of embankment that washed away during the December atmospheric river weather event. They also repaved and installed striping and guardrail. pic.twitter.com/EEra1HTgeL
— WSDOT North (@wsdot_north) January 21, 2026
SR 530 previously closed due to flood damage
In mid-December, WSDOT closed all lanes of eastbound and westbound SR 530 from Suiattle River Road to Concrete Sauk Valley Road.
SR 530 remained closed for more than a month as crews worked to fortify the shoulder that was damaged by the floodwaters.
At the time, WSDOT’s goal was to reopen the highway as soon as it was safe for travel, even if only a single lane could be used for alternating traffic initially.