Tour the SR 99 tunnel: Crews finish roadways inside the passage

Mar 27, 2018, 1:09 PM | Updated: 1:42 pm

Crews working under Seattle have hit a milestone as the SR 99 tunnel takes shape.

The final panel of the lower deck was installed this month (northbound lanes). The northbound stretch is constructed of 1,152 panels. Both levels — north and southbound — are now finished inside the SR 99 tunnel.

RELATED: Seattle council say goodbye to Battery Street Tunnel

Crews are not finished, however. There are still 300 traffic-monitoring cameras to test; ventilation systems to get up and running; and automated sprinkler systems to put out fires inside the tunnel. WSDOT says that “together, these systems will make the SR 99 tunnel one of the ‘smartest’ tunnels ever built.” The tunnel will be a living, breathing machine once it is finished. The two minute drive under Seattle will require an operation with control centers and mechanical systems for air, water, communication, power supply, and more.

Here’s a video from WSDOT showing the final piece of roadway being installed.

Tour the SR 99 tunnel

KIRO Radio’s Traffic Reporter Chris Sullivan toured the SR 99 tunnel. See his findings below.

Chokepoints

amtrak seattle portland service...

MyNorthwest Staff

Amtrak Seattle-Portland service suspended until Wednesday morning after Portland warehouse fire

Amtrak's train service between Seattle and Portland is currently suspended, and it won't return until Wednesday morning.

2 hours ago

sound transit 1 line...

Nate Connors

Sound Transit 1-Line replaced by shuttle buses this week in the south end

Sound Transit's 1-Line will switch to shuttle bus service between Rainier Beach and Angle Lake Station, just south of Seattle-Tacoma International Airport (SEA).

3 hours ago

wire theft...

Chris Sullivan

‘A well-oiled machine’: Wire theft rings are outpacing WSDOT’s efforts to protect I-5 infrastructure

Wire theft continues to cost the Washington Department of Transportation (WSDOT) and taxpayers hundreds of thousands of dollars every year.

4 hours ago

construction roadways weekend...

Paola Tristan Arruda, KIRO 7 News

Prepare for another weekend of major construction on three roadways

Travelers in the Puget Sound region should prepare for delays and road closures this weekend as construction takes place across I-405, SR 99, and I-5.

3 days ago

A photo of the northbound I-5 closure near Everett. (Photo courtesy of the Washington State Departm...

Jason Sutich

25-year-old man arrested after climbing, hanging from I-5 overpass near Everett

A 25-year-old man was arrested after climbing and hanging from an I-5 overpass near Everett, prompting officials to shut down all lanes in the area.

4 days ago

tiger mountain sr 18 blocked...

Jason Sutich

All lanes of SR 18 reopen after semi-truck, motorcycle collision near Tiger Mountain

All lanes of SR 18 near Tiger Mountain have reopened after a semi-truck and motorcycle collision.

4 days ago

Tour the SR 99 tunnel: Crews finish roadways inside the passage