Washington ferry system blames Trump tariffs for rising Colman Dock costs

Feb 28, 2019, 5:52 AM | Updated: 12:29 pm

Colman Dock...

Colman Dock ferry terminal. (KIRO 7)

(KIRO 7)

Washington state is about two years into the massive renovation of Colman Dock in downtown Seattle, and the price-tag continues to rise by the millions, thanks in part to the Trump Administration’s tariff’s on foreign steel.

RELATED: 25 million ferry riders in 2018; most in 16 years
RELATED: 2K reports of drivers cutting in ferry line

The 25 percent tariff imposed on foreign steel caused U.S. steel prices to jump significantly in the first few months, but they have since returned to pre-tariff levels. Despite that return to lower costs, the head of the state ferry system, Amy Scarton, blamed steel prices for pushing the Colman Dock retrofit into the red. She said as much during a briefing in Olympia this week.

“We have seen quite a bit of cost increase in those steel prices, just since last fall, when I believe the tariffs went up,” Scarton told the Senate Transportation Committee. “That is probably the number-one cost driver of the section of our request that is asking for a cost increase. It’s steel.”  The ferry system said it has seen a 24 percent increase in their steel costs

Scarton asked the committee for another $95 million, testifying the original didn’t fully fund the project.

“It did not fund everything we needed to get done in the project, over six years,” she said. “It essentially funded what we needed in that first biennium to get the project started.”

The project is now estimated to cost $468 million, which is significantly higher than the original price-tag. Senator Curtis King told Scarton that project managers should be able to do a better job controlling costs.

“We seem to have just gone a little overboard in trying to accommodate everybody and everything and not paid a lot of attention to how this was done and who’s going to get to pay for it,” he said.

Ferry system engineer Nicole McIntosh answered Senator King, testifying that the agency is watching costs closely.

“We do, as we go through design, look at practical design,” McIntosh said. “The terminal building that we’re building is actually smaller than the one we have today because we right-sized it, which is our attempt to minimize the cost.”

The entire north end of the dock is now closed, as workers remove all the old wooden pilings that have held it up for far too long. Those creosote pilings are being replaced by steel. Later this year, the terminal building will come down. The passenger-only ferry slip should be open over the summer. It moves the King County Water Taxi and Kitsap ferries to a permanent home on the south end of the dock.

The entire project should be finished by 2023.

Chokepoints

seattle traffic...

Nate Connors

Major sports events, full closure on I-405 will make for very busy Seattle commute all weekend

This weekend around the Seattle area might go down as one of the busiest of the summer for the Washington State Department of Transportation.

2 days ago

traffic highway closures...

Paola Tristan Arruda, KIRO 7 News

TRAFFIC: Major highway closures across Puget Sound this weekend

Drivers across the Puget Sound should prepare for one of the busiest travel weekends of the summer.

2 days ago

i-5 south tacoma crash...

KIRO 7 News Staff

I-5 northbound fully blocked in South Tacoma after crash involving up to 10 cars

The northbound lanes of Interstate 5 were fully blocked in South Tacoma early Friday morning after a multi-car crash involving a semi-truck.

3 days ago

Hood Canal Bridge (1)...

MyNorthwest Staff

Stalled semitruck cleared after blocking Hood Canal Bridge for more than an hour

A stalled semitruck was blocking the entrance to the Hood Canal Bridge.

3 days ago

A photo of the overturned dump truck. (Photo courtesy of the Washington State Patrol)...

KIRO 7 News Staff

Truck overturns, spilling dirt and blocking ramp from I-5 to State Route 167

The ramp from northbound Interstate 5 to State Route 167 in Pierce County is fully blocked because of an overturned dump truck.

4 days ago

washington ferry ferguson...

MyNorthwest Staff

Washington breaks ground on first new ferry in 11 years, three hybrid-electric vessels ordered

Governor Bob Ferguson announced construction is underway on the state's first new ferry in 11 years, stating a third hybrid-electric vessel has now been added to the order.

5 days ago

Washington ferry system blames Trump tariffs for rising Colman Dock costs