West Seattle Bridge opening delayed another two months

Jun 9, 2022, 4:10 PM | Updated: Jun 10, 2022, 8:53 am

West Seattle Bridge...

Crews at the West Seattle Bridge (SDOT)

(SDOT)

West Seattle residents are going to have to wait until September before the high bridge reopens.

The scheduled early summer reopening has been pushed back more than two months because of the King County concrete strike earlier this year.  The contractor had planned to pour the concrete for the steel support beams inside the bridge at the start of the year.  Seattle Mayor Bruce Harrell set a February 20 deadline for the strike to end before the reopening would be impacted.  The concrete didn’t arrive until mid-April.

Concrete strike’s impact on West Seattle Bridge timeline unclear as SDOT makes final pours

There had been hope that the contractor could make up the time and keep the schedule somewhat intact, but that didn’t happen.  The two-month delay in getting the concrete after that deadline turned into a two-month delay in the reopening.

Work on the bridge was scheduled to end in June, and then open to traffic after a few days of load testing to make sure the bridge was ready for cars.

“It’s been hard having to wait for this update, but we did need to get through the concrete work to understand exactly where we were schedule-wise,” SDOT Program Manager Heather Marx said in a statement.  The earliest the bridge will reopen is September 12.

It’s also possible that the date could slide as well.  The remaining repair work is difficult.  “We know that all of West Seattle, South Park, and Georgetown have had the bridge reopening top of
mind since it closed. I am still holding out hope for a summer re-opening, but I appreciate SDOT’s announcement today; it lets us know that we’re close – just three months away,” City Councilmember Lisa Herbold said in a statement.”

The bridge closed to traffic in March of 2020 after cracks inside the bridge started growing too fast.  The reason for the failure was bad steel used to support the concrete.

Check out more of Chris’ Chokepoints.

Chokepoints

ritzville i-90 closed visibility...

Jason Sutich

I-90 in Ritzville reopens after dust storm caused multiple collisions

I-90 in Ritzville has reopened after both directions were blocked Friday due to multiple collisions.

11 hours ago

super load marysville...

Chris Sullivan

Super load stuck on I-5 south in Marysville should move tonight

A truck carrying a massive pre-fab building has been parked along the southbound I-5 ramp at 88th St. in Marysville for three days.

17 hours ago

closure (1)...

MyNorthwest Staff

I-5 reopens in both directions between Maytown and Tumwater

I-5 has reopened in both directions in Thurston County at milepost 97, KIRO Newsradio confirmed.

18 hours ago

oyster run anacortes...

Nate Connors

43rd annual Oyster Run returns this weekend in Anacortes

The Oyster Run welcomes thousands of motorcyclists to Skagit County by Figaldo Bay. It's loud, it's proud, and it takes over Anacortes this time each year.

1 day ago

sounder train shoreline...

MyNorthwest Staff

All S Line trains stopped after woman hit in SODO

All Sound Transit S Line trains have been stopped after a woman was hit in SODO Thursday.

2 days ago

Pinehurst Station light rail...

Chris Sullivan

Sound Transit to open new light rail station 5 years ahead of schedule

Sound Transit isn't known for being on time or on budget with its light rail projects, but it's about to open a new station way ahead of schedule.

2 days ago

West Seattle Bridge opening delayed another two months