CHOKEPOINTS

West Seattle Bridge opening delayed another two months

Jun 9, 2022, 4:10 PM | Updated: Jun 10, 2022, 8:53 am

West Seattle Bridge...

Crews at the West Seattle Bridge (SDOT)

(SDOT)

West Seattle residents are going to have to wait until September before the high bridge reopens.

The scheduled early summer reopening has been pushed back more than two months because of the King County concrete strike earlier this year.  The contractor had planned to pour the concrete for the steel support beams inside the bridge at the start of the year.  Seattle Mayor Bruce Harrell set a February 20 deadline for the strike to end before the reopening would be impacted.  The concrete didn’t arrive until mid-April.

Concrete strike’s impact on West Seattle Bridge timeline unclear as SDOT makes final pours

There had been hope that the contractor could make up the time and keep the schedule somewhat intact, but that didn’t happen.  The two-month delay in getting the concrete after that deadline turned into a two-month delay in the reopening.

Work on the bridge was scheduled to end in June, and then open to traffic after a few days of load testing to make sure the bridge was ready for cars.

“It’s been hard having to wait for this update, but we did need to get through the concrete work to understand exactly where we were schedule-wise,” SDOT Program Manager Heather Marx said in a statement.  The earliest the bridge will reopen is September 12.

It’s also possible that the date could slide as well.  The remaining repair work is difficult.  “We know that all of West Seattle, South Park, and Georgetown have had the bridge reopening top of
mind since it closed. I am still holding out hope for a summer re-opening, but I appreciate SDOT’s announcement today; it lets us know that we’re close – just three months away,” City Councilmember Lisa Herbold said in a statement.”

The bridge closed to traffic in March of 2020 after cracks inside the bridge started growing too fast.  The reason for the failure was bad steel used to support the concrete.

Check out more of Chris’ Chokepoints.

Chokepoints

seattle traffic...

Nate Connors

Major sports events, full closure on I-405 will make for very busy Seattle commute all weekend

This weekend around the Seattle area might go down as one of the busiest of the summer for the Washington State Department of Transportation.

17 hours ago

traffic highway closures...

Paola Tristan Arruda, KIRO 7 News

TRAFFIC: Major highway closures across Puget Sound this weekend

Drivers across the Puget Sound should prepare for one of the busiest travel weekends of the summer.

23 hours ago

i-5 south tacoma crash...

KIRO 7 News Staff

I-5 northbound fully blocked in South Tacoma after crash involving up to 10 cars

The northbound lanes of Interstate 5 were fully blocked in South Tacoma early Friday morning after a multi-car crash involving a semi-truck.

1 day ago

Hood Canal Bridge (1)...

MyNorthwest Staff

Stalled semitruck cleared after blocking Hood Canal Bridge for more than an hour

A stalled semitruck was blocking the entrance to the Hood Canal Bridge.

2 days ago

A photo of the overturned dump truck. (Photo courtesy of the Washington State Patrol)...

KIRO 7 News Staff

Truck overturns, spilling dirt and blocking ramp from I-5 to State Route 167

The ramp from northbound Interstate 5 to State Route 167 in Pierce County is fully blocked because of an overturned dump truck.

2 days ago

washington ferry ferguson...

MyNorthwest Staff

Washington breaks ground on first new ferry in 11 years, three hybrid-electric vessels ordered

Governor Bob Ferguson announced construction is underway on the state's first new ferry in 11 years, stating a third hybrid-electric vessel has now been added to the order.

3 days ago

West Seattle Bridge opening delayed another two months