WSDOT working overtime to reopen passes for busy holiday travel

May 15, 2026, 3:16 PM | Updated: 3:19 pm

wsdot passes holiday travel...

Work to stabilize the slope near milepost 131 began on Tuesday, May 5. Crews are performing scaling, which is closely inspecting the slope and using hand tools and air compression to dislodge loose rocks and debris. (Photo courtesy of WSDOT)

(Photo courtesy of WSDOT)

North Cascades Highway

The final stretch of emergency repairs is underway along a closed section of the North Cascades Highway/SR 20 between Colonial Creek Campground (milepost 130) and Porcupine Creek (milepost 156). Contractors will work 24/7 to reopen the highway by June 25, according to the Washington State Department of Transportation (WSDOT).

WSDOT selected Trimaxx Construction Inc. for the new contract to perform repairs along a six-mile stretch of SR 20 between Canyon Creek Trailhead and Granite Creek (mileposts 142 to 148). Trimaxx was the contractor that repaired a section of SR 530 that the Sauk River washed out during the December atmospheric river storms and flooding.

The damaged area that Trimaxx will repair along SR 20 includes:

  • Three locations where the embankment supporting the roadway needs rebuilding
  • More than 1,000 feet of lane has been undermined or collapsed
  • Approximately two miles of damaged or collapsed asphalt shoulder
  • Approximately three miles of ditch line need to be repaired
  • More than 1,000 feet of damaged guardrail and concrete barrier
  • Approximately 15 culverts are damaged or covered by debris

Initial emergency repairs

Interwest Construction Inc. of Burlington began emergency work on SR 20 earlier this month to stabilize a slope and clear debris from a March rockslide near Diablo Lake (milepost 131). Work at both sites will take place simultaneously.

Crews recently completed dislodging loose rocks and debris from the slope using hand tools and air compressors. They’re now hauling away the last of the debris and drilling holes in the rock face so that long steel dowels can be anchored to stabilize the slope. The steel dowels range from 20 to 60 feet long and are placed as directed by WSDOT geotechnical engineers, carefully examining the slope as work progresses.

Active work zone off-limits

The closed section of SR 20 between mileposts 130 and 156 will remain an active work zone until repairs are complete. Work is expected around the clock in a narrow corridor, and no unauthorized people are allowed.

There is no safe way to allow public access through the area, including hiking, biking, or camping, until work is complete and SR 20 reopens. Portable electronic signs are posted at both ends of the closure, reminding people that no access is permitted.

Chinook Pass/Cayuse Pass

The Washington State Department of Transportation (WSDOT) is in the final stage of clearing a path over Mount Rainier National Park, which closes each winter due to heavy snow and increased avalanche danger.

This includes the combination of two passes, Chinook/SR 410 and Cayuse/SR 123. WSDOT has already cleared both highways of snow and has moved to the final phase of clearing Stevens Canyon Road and Sunrise Park Road. WSDOT has stated that they plan to reopen this route at 8 a.m. Friday, May 22, in time for Memorial Day Weekend.

As a reminder, all commercial vehicles are prohibited from traveling through Mount Rainier National Park, which includes sections of SR 123 and SR 410.

Nate Connors is a traffic reporter for KIRO Newsradio. Follow him on X. Read more of his stories here. Submit news tips here.

Chokepoints

Sound Transit budget deficit delays...

John Curley Show

‘Almost no accountability’: Transportation expert says Sound Transit is ‘building for the past’ amid ballooning budget

KIRO host John Curley, a longtime skeptic of public transportation and its ballooning costs, brought on Charles Prestrud to discuss where Sound Transit went wrong.

10 hours ago

SR 202...

Chris Sullivan

SR 202 near Fall City to close this weekend for emergency river embankment repairs

Work is moving to SR 202 near Fall City this week, creating a 16-mile detour for people trying to get around the area.

18 hours ago

SR 20...

KIRO 7 News Staff

Westbound SR 20 closed for a semi-truck off the road

According to Trooper Kelsey Harding, shortly before 6:30 p.m. Monday, a semi-truck went off the road on SR 20 just east of SR 9.

1 day ago

SEA ground stop thunderstorm...

Jason Sutich

Ground delay at SEA Airport after thunderstorms hit the region

A ground delay has been issued for flights arriving at Seattle-Tacoma International Airport after thunderstorms swept through the region Thursday.

6 days ago

Drivers use the High Occupancy Vehicle (HOV) lane, also called the diamond or commuter lane. (Photo...

Chris Sullivan

When is a left lane camper not really camping?

Is there anything worse than a left lane camper? It's time for a reminder on what is and isn't the congestion-causing behavior that drives us nuts.

6 days ago

revive I-5 tolls I-405 commute...

Chris Sullivan

90-minute morning commutes return as Revive I-5 swings back into action

As expected, the drives out of Snohomish County were awful, some of the worst travel times we've seen since the project started again in January.

7 days ago

WSDOT working overtime to reopen passes for busy holiday travel