Alaskan Way Viaduct demolition hits delays in central core

Apr 22, 2019, 9:08 AM | Updated: 10:08 am

The demolition of the Alaskan Way Viaduct is taking longer than expected, with at least “a couple weeks” of delays expected for the central section of the now-closed roadway.

RELATED: Alaskan Way Viaduct officially starts to come down

Ivar’s president Bob Donegan told The Seattle Times that the demolition process for the large, central section will likely take until June 22, weeks later than the original June 1 target date set by Kiewit Infrastructure West.

“It’s disappointing, that when someone gives you a commitment and doesn’t fulfill it, especially in our busiest period during the summer,” Donegan told the Times.

In February, crews estimated that the removal of each deck section would take 0.6 days. In reality, it’s taken between 1.3 and 1.7 days.

According to WSDOT’s live demolition tracker (last updated April 12), just a handful of sections down near Pike Place Market have been completely removed and restored since the project began back in February.

Demolition at the northern end of the viaduct extending down to Lenora is currently in the final “site restoration” phase before completion, while work has yet to begin on the southern end past Yesler Way.

WSDOT is now “looking for efficiencies to speed up the work,” and hopes that delays for the central core of sections will be limited to less than three weeks.

When it’s all said in done, almost two miles of roadway will be removed, comprised of 400 columns, and 61,000 cubic yards of concrete, weighing 122,000 tons. The hope is to have the entire viaduct removed by the end of summer in August.

MyNorthwest News

Kitsap County Sheriff burning SUV crash...

KIRO 7 News Staff

Kitsap Co. deputies rescue man from burning SUV after police chase crash

The Kitsap County Sheriff’s Office posted body cam video of deputies rescuing a man they said crashed after speeding away from police before his car caught fire.

31 minutes ago

south seattle building fire...

KIRO 7 News Staff

South Seattle building fire extinguished

A fire at a commercial building in South Seattle early Wednesday morning prompted a large response from Seattle firefighters and temporarily shut down traffic along 4th Avenue S.

1 hour ago

outage revenue businesses seattle...

Nia Bliss, KIRO 7 News

Seattle businesses say short notice for multi-day planned outages led to revenue losses

Multiple businesses in Seattle’s Chinatown-International District said they were given short notice for planned power outages between Sept. 14 and 17.

1 hour ago

fall...

Ted Buehner

Dry weather this week offers perfect window for fall color viewing in Washington

The fall season is here. This season is the time of year when tree leaves change colors, offering a collection of vibrant autumn hues.

3 hours ago

closures...

Nate Connors

Plan ahead: WSDOT has a number of late night closures around the region this week

The final week of Summer is a busy one for WSDOT, as it races to complete as many projects as they can before the fall rains arrive.

13 hours ago

mitten crabs wa guilty plea...

Jason Sutich

AG’s office secures guilty plea in illegal distribution of invasive mitten crabs in WA

The Washington Attorney General's Office secured a guilty plea from an individual who attempted to distribute invasive mitten crabs in violation of state law.

13 hours ago

Alaskan Way Viaduct demolition hits delays in central core