The demolition of the Alaskan Way Viaduct is taking longer than expected, with at least “a couple weeks” of delays expected for the central section of the now-closed roadway.

RELATED: Alaskan Way Viaduct officially starts to come down

Ivar’s president Bob Donegan told The Seattle Times that the demolition process for the large, central section will likely take until June 22, weeks later than the original June 1 target date set by Kiewit Infrastructure West.

“It’s disappointing, that when someone gives you a commitment and doesn’t fulfill it, especially in our busiest period during the summer,” Donegan told the Times.

In February, crews estimated that the removal of each deck section would take 0.6 days. In reality, it’s taken between 1.3 and 1.7 days.

According to WSDOT’s live demolition tracker (last updated April 12), just a handful of sections down near Pike Place Market have been completely removed and restored since the project began back in February.

Demolition at the northern end of the viaduct extending down to Lenora is currently in the final “site restoration” phase before completion, while work has yet to begin on the southern end past Yesler Way.

WSDOT is now “looking for efficiencies to speed up the work,” and hopes that delays for the central core of sections will be limited to less than three weeks.

When it’s all said in done, almost two miles of roadway will be removed, comprised of 400 columns, and 61,000 cubic yards of concrete, weighing 122,000 tons. The hope is to have the entire viaduct removed by the end of summer in August.

Please follow our Community Guidelines

MyNorthwest News

parenting...

Katrina Guischard

The parenting advice going viral right now: be the pilot, not the passenger

An expert is challenging some of today's most popular parenting trends, and it's striking a chord.

4 hours ago

ritzville i-90 closed visibility...

Jason Sutich

I-90 in Ritzville reopens after dust storm caused multiple collisions

I-90 in Ritzville has reopened after both directions were blocked Friday due to multiple collisions.

14 hours ago

Ballard hit-and-run...

KIRO Newsradio staff

20-year-old sentenced to more than 3 years for deadly 2025 Ballard hit-and-run

The man accused in the hit-and-run death of a pedestrian in Ballard last year has been sentenced to more than three years in prison.

15 hours ago

2 box truck fire SODO...

Julia Dallas

Suspects accidentally light themselves on fire while allegedly trying to steal fuel from box trucks in SODO

Two suspects accidentally set themselves on fire while they appeared to be trying to steal fuel from box trucks in the SODO neighborhood.

16 hours ago

columbia city school gun...

MyNorthwest Staff

Person in custody after gun seized by staff at high school in Seattle

A person is in custody after a gun was seized by staff at a high school in Seattle.

17 hours ago

2 Rick Rizzs...

Manda Factor

Rick Rizzs says goodbye to Mariners booth after 52-year career: ‘I’ve lived my dream’

Rick Rizzs has three games left behind the microphone for the Seattle Mariners, and a lifetime of memories competing for his attention.

17 hours ago

Alaskan Way Viaduct demolition hits delays in central core