Bertha has stopped under this downtown Seattle street

Oct 25, 2016, 5:44 AM | Updated: 5:48 am

Bertha...

A carved pumpkin -- with Bertha on it -- and some balloons mark the block along 1st Avenue where Bertha is currently stopped under. (WSDOT)

(WSDOT)

Bertha has now bored more than 5,000 feet under downtown Seattle, and has stopped under one of the city’s more popular destinations.

Tunnel crews have bored 5,085 feet — out of 9,270 feet — and crews have constructed 774 rings in Bertha’s wake. It’s currently in the middle of Zone 6 — out of 10 zones. More specifically, the machine is about 200 feet below First Avenue just past Pine Street. This is nearing the deepest the machine will be on its journey under Seattle.

How Seattle soil wears down Bertha

The block between Pine Street and Stewart Street along First Avenue is rather short, and that is where Bertha is currently undergoing a maintenance stop. There are three buildings on this block — a hotel/motel built in 1985; an apartment building, with retail below, built in 1909; and an office building built in 1986.

This spot is also one short block away from Seattle’s popular tourist destination, Pike Place Market.

After passing through Zone 6, Bertha will have passed underneath a railroad tunnel built in 1904, and a major sewer tunnel that connects downtown to the West Point Treatment Plant. It will have also passed Pike Place Market to its left.

Bertha under pressure

The stop is for more maintenance — basically, crews have to crawl around the front of Bertha to see if any of the cutter heads are worn down. There are more than 700 cutting tools at the front. The tools can weigh hundreds of pounds. This is the third and final such maintenance stop for Bertha this year.

The maintenance stop will include hyperbaric work, meaning that crews must go through a chamber and adjust to the higher pressure in the tunnel in order to do the work. It’s a lengthy process. The Washington State Department of Transportation notes that past stops have taken around seven weeks, but crews are considering stopping for a shorter time during these final stops, yet more frequently.

Please follow our Community Guidelines

MyNorthwest News

Police tape runs across a crime scene. (Photo courtesy of KIRO 7)...

Tom Brock

Tacoma police investigate downtown shooting that left a teenager dead

A shooting early Sunday in downtown Tacoma has taken a teenager's life.

15 hours ago

kids consequences accountability...

Katrina Guischard

Stop rescuing your kids? Psychiatrist says raising kids with accountability starts with small consequences

Parents, how many times have you rescued your kid’s forgotten homework, packed the lunch they forgot, or rushed a jacket to school because they were cold?

1 day ago

Firefighters prevented a smoky commercial fire from spreading to other businesses in Edmond's Westg...

Tom Brock

Fire heavily damages gyro shop in south Everett

Fire crews prevented a smoky fire from spreading at a business in the Westgate neighborhood of Edmonds Saturday morning.

2 days ago

Demonstrators hold up banners as they march across the Memorial Bridge during a No Kings protest in...

MyNorthwest News Staff and Associated Press

No Kings protests and marches in Seattle and across the country encourage early voting

The city of Seattle's Transportation Department issued a warning to drivers Saturday to expect delays due to a "No Kings" rally and march through downtown Seattle.

2 days ago

Georgetown cabaret shooting...

James Lynch

Reward now $15,000 in deadly Georgetown cabaret shooting

The reward for information leading to an arrest and charge in a deadly shooting at Kitten’s Cabaret in Georgetown has increased to $15,000.

3 days ago

I-405 (3)...

Nate Connors

WSDOT projects over the weekend include another closure on I-405

The good news is this weekend's list of WSDOT projects is substantially shorter. The bad news is we have another full closure on I-405.

3 days ago

Bertha has stopped under this downtown Seattle street