Bertha contractors want WSDOT to pay for sinkhole stoppage

Feb 23, 2016, 12:46 PM | Updated: 10:35 pm

WSDOT has given permission for Bertha to start digging again underneath Seattle’s waterfront,...

WSDOT has given permission for Bertha to start digging again underneath Seattle's waterfront, under certain conditions. (WSDOT)

(WSDOT)

Bertha is allowed to dig under Seattle once again.

The contractor, Seattle Tunnel Partners, has been given conditional permission to start tunneling underneath the city’s waterfront after nearly a month of halted operations.

Related: Gov. Inslee says STP is downplaying the significance of sinkholes

“WSDOT, in consultation with its team of tunnel experts, lifted the suspension of tunneling for cause and said that conditional tunneling should resume for 25 more tunnel rings. I concur with their decision, and WSDOT has notified the contractor,” said Gov. Jay Inslee on Tuesday.

The permission is conditional, according to the Washington State Department of Transportation. Bertha is allowed to move ahead approximately 160 feet, and install about 25 concrete rings to continue crafting the tunnel. WSDOT will monitor the progress to see if STP can prove it can operate the machine safely. If WSDOT approves of STP’s operations, Bertha will be allowed to move ahead another 100 feet to its planned maintenance stop. That stop is the waypoint before tunneling underneath the Alaskan Way Viaduct and downtown Seattle.

STP was given permission Tuesday morning. Tunneling began at around 7 a.m. By 3:30 p.m., Bertha had moved forward about 3 feet.

Conflict between STP and WSDOT

Despite the approval to move forward, the stoppage over the past month has caused another rift between WSDOT and the tunneling contractor.

“There is a disagreement with Seattle Tunnel Partners on this. It’s not the first time we have disagreed,” said Todd Trepanier with WSDOT. “They think the stop was not appropriate, and they would like to be compensated for the time it has cost them.”

Trepanier said that if STP decides to press the issue and demand compensation, WSDOT will use dispute resolution mechanisms in the contract for the project.

Conditional permission

Even though WSDOT is allowing STP to bore once more, barging activity &#8212 the process of shipping away excavated soils via barges in Elliott Bay &#8212 will be restricted until further procedures are developed. In the meantime, the soil will be shipped away by truck. It’s that process that has been under scrutiny after a sinkhole developed in Bertha’s wake in January.

“The contractor has a plan for modifying tunnel operations to ensure positive ground control. It has also made changes to key personnel, and it has put in place protocols for quality control and assurance,” Inslee said. “The contractor now has an opportunity to show progress during this test period, prior to tunneling under the viaduct and underneath Seattle.”

Related: Renowned architect says sinkhole is the second big mistake for Bertha

WSDOT has placed conditional changes to operations, which include:

• Update the tunnel work and plans, including calculations of the amount of soil removed while digging
• Reorganize personnel within STP’s quality assurance department
• Implement new quality assurance procedures
• Personell at key tunneling positions will be changed
• New daily tunneling meetings with more participants and procedures

The project to dig a tunnel to replace the SR 99 viaduct through downtown Seattle has faced a series of problems that have stopped its progress. Most recently, the machine caused a sinkhole shortly after starting up again. That start was highly anticipated after it sat idle for repairs for nearly two years.

After the sinkhole developed, the state halted all operations of the tunneling project until STP could prove the job could be done safely.

Sign up for breaking news alerts

Please follow our Community Guidelines

MyNorthwest News

Sound Transit budget deficit delays...

Michael Strite

Sound Transit to host community forum after Ballard light rail delayed to 2042

Sound Transit is encouraging Seattle residents to speak up about the proposed light rail extension to the Ballard neighborhood.

20 minutes ago

SR 18 crash tiger mountain...

Frank Sumrall

Crash near Tiger Mountain summit shuts down all westbound SR 18 lanes

All westbound lanes of SR 18 were blocked at I-90 in Snoqualmie for nearly an hour due to a crash near the Tiger Mountain summit.

46 minutes ago

bird flu...

KIRO 7 News Staff

Yakima resident tests positive for bird flu

A person in Yakima County has tested positive for avian flu, otherwise known as bird flu, according to the Yakima Health District and Washington State Department of Health.

1 hour ago

Grays Harbor County Bus Crash...

KIRO 7 News Staff

One dead, two injured after head-on crash with transit bus in Grays Harbor County

One person is dead after colliding head-on with a transit bus in Grays Harbor County, Washington State Patrol (WSP) Trooper Katherine Weatherwax confirmed Sunday night.

1 hour ago

Police tape runs across a crime scene. (Photo courtesy of KIRO 7)...

Tom Brock

Tacoma police investigate downtown shooting that left a teenager dead

A shooting early Sunday in downtown Tacoma has taken a teenager's life.

17 hours ago

kids consequences accountability...

Katrina Guischard

Stop rescuing your kids? Psychiatrist says raising kids with accountability starts with small consequences

Parents, how many times have you rescued your kid’s forgotten homework, packed the lunch they forgot, or rushed a jacket to school because they were cold?

1 day ago

Bertha contractors want WSDOT to pay for sinkhole stoppage