MYNORTHWEST NEWS

Bertha in ‘good’ shape, no timetable to resume tunneling

Jan 24, 2014, 1:10 PM | Updated: 2:03 pm

A deliberate, meticulous inspection of the tunneling machine beneath downtown Seattle has still not revealed why “Bertha” is stopped in her tracks.

The $80 million boring machine is about 1,000 feet into its 1.7 mile-long job.

Seattle Tunnel Partners and its tunneling contractor have inspectors in a protected chamber in front of Bertha, rotating and examining the cutting surfaces.

“We know that the contractor really hasn’t found anything that would indicate further what may have caused the stoppage issue that we have here,” said Matt Preedy, a deputy administrator with the Washington State Department of Transportation, which is overseeing the project.

There is still no estimate as to when boring might resume.

Meantime, Preedy took reporters and photographers 80 feet below the surface Friday to near the entrance of the tunnel to show the progress underway on other parts of the Alaskan Way Viaduct replacement project.

“There’s over 300 people working on the site each and every day and we’re standing right here in the middle of a 600-foot long piece of what we call the cut-and-cover roadway, south of the tunnel and this is the piece of infrastructure that gets the cars and traffic from underground to above ground,” Preedy explained.

The boring machine hit a steel casing in early December and then stopped digging altogether on Dec. 7. So far, Preedy said inspections of the cutting face reveal no significant damage or unusual wear and tear.

MyNorthwest News

A Coast Guardsman tosses a rope to a kayaker in distress after the kayaker's boat overturned north ...

Tom Brock

San Juan Islands Rescue: Coast Guard crews save man after his kayak overturns

A Coast Guard helicopter and rescue boat saved a man from the chilly waters of the Salish Sea Friday, after his kayak capsized near Orcas Island.

6 hours ago

Boeing (2)...

Tom Brock

Software glitch raises safety concerns for Boeing 737 MAX planes

Boeing has notified its customers of a computer glitch on its 737 MAX planes that could force pilots to land manually, instead of using autopilot.

7 hours ago

seattle ranking cities...

MyNorthwest Staff

Seattle earns 4th-highest ranking in the world in new study of 1,000 cities

A new study ranks Seattle 4th globally, highlighting governance, economics, and quality of life among cities.

11 hours ago

parenting...

Katrina Guischard

The parenting advice going viral right now: be the pilot, not the passenger

An expert is challenging some of today's most popular parenting trends, and it's striking a chord.

1 day ago

ritzville i-90 closed visibility...

Jason Sutich

I-90 in Ritzville reopens after dust storm caused multiple collisions

I-90 in Ritzville has reopened after both directions were blocked Friday due to multiple collisions.

2 days ago

Ballard hit-and-run...

KIRO Newsradio staff

20-year-old sentenced to more than 3 years for deadly 2025 Ballard hit-and-run

The man accused in the hit-and-run death of a pedestrian in Ballard last year has been sentenced to more than three years in prison.

2 days ago

Bertha in ‘good’ shape, no timetable to resume tunneling